2115 1/2 S RIMPAU BLVD 90016

Certificate Information: 2115 1/2 S RIMPAU BLVD 90016

Application / Permit
24016-10000-17264
Plan Check / Job No.
B24LA09991
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
495 SQFT GARAGE CONVERSION + 75 SQFT TO CREATE AN ADU PER STATE LAW
Permit Issued
Issued on 1/14/2025
Issuing Office
Metro
Current Status
CofO Issued on 8/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/29/2024 NEHEMIAS RAMOS
Corrections Issued 6/2/2024 NEHEMIAS RAMOS
Building Plans Picked Up 6/6/2024 APPLICANT
Applicant returned to address corrections 11/15/2024 EDWIN MARTINEZ
Plan Check Approved 12/6/2024 ALEXANDER JOO
Issued 1/14/2025 APPLICANT
CofO in Progress 7/28/2025 JUSTIN HAWLEY
Permit Finaled 8/1/2025 DEROLD HAUFF
CofO Issued 8/1/2025 DEROLD HAUFF
Permit Finaled 8/1/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 6/13/2024 EDGAR PASCUA
Address approval Cleared 6/14/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 6/14/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/22/2024 WALLIE JONG
Sewer availability Cleared 10/22/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/26/2025 Conditional Approval ALEX COLIN
Footing/Foundation/Slab 2/27/2025 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 3/3/2025 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 3/27/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 4/10/2025 Partial Inspection FREDDIE RIVERA
Gas Test 4/10/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 4/10/2025 Partial Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 4/10/2025 Partial Inspection FREDDIE RIVERA
Underground Mechanical 4/10/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 4/14/2025 Corrections Issued JOSE MACIAS
Gas Test 4/14/2025 Approved JOSE MACIAS
HVAC-Rough 4/14/2025 Approved JOSE MACIAS
PLUMBING-Rough 4/14/2025 Approved JOSE MACIAS
Sewer 4/14/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 4/22/2025 Approved ENRIQUE MIRELES
Gas Test 4/22/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/22/2025 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/22/2025 Approved ENRIQUE MIRELES
Sewer 4/22/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/30/2025 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved JOSE MACIAS
Green Building Rough 4/30/2025 Approved JOSE MACIAS
Insulation 4/30/2025 Approved JOSE MACIAS
MERV13>=Rough 4/30/2025 Approved JOSE MACIAS
Drywall Nailing 5/9/2025 Approved ALEX COLIN
Insulation 5/9/2025 Approved ALEX COLIN
Interior/Exterior Lathing 5/9/2025 Approved ALEX COLIN
Shower Pan 5/9/2025 Approved ALEX COLIN
ELECTRICAL-Rough 6/5/2025 Not Ready for Inspection JUSTIN HAWLEY
Underground Mechanical 6/5/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Final 7/16/2025 Not Ready for Inspection JUSTIN HAWLEY
Final 7/16/2025 Corrections Issued JUSTIN HAWLEY
Gas Test 7/16/2025 Approved JUSTIN HAWLEY
HVAC-Final 7/16/2025 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 7/28/2025 Approved JUSTIN HAWLEY
Final 7/28/2025 OK to Issue CofO JUSTIN HAWLEY
Footing/Foundation/Slab 7/28/2025 Approved JUSTIN HAWLEY
Gas Test 7/28/2025 Approved JUSTIN HAWLEY
Green Building Final 7/28/2025 Approved JUSTIN HAWLEY
HVAC-Final 7/28/2025 Approved JUSTIN HAWLEY
MERV13>=Final 7/28/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 7/28/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 7/28/2025 Approved JUSTIN HAWLEY