126 N SAN PASCUAL AVE 90042
Certificate Information: 126 N SAN PASCUAL AVE 90042
- Application / Permit
- 24016-10000-17172
- Plan Check / Job No.
- B24LA09942
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install new Ordinary Steel Moment Frame and Special Steel Cantilever Columns
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Current Status
- CofC Issued on 2/3/2025
Permit Application Status History
| Submitted | 5/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | HANS SANTIAGO |
| Corrections Issued | 6/3/2024 | HANS SANTIAGO |
| Quality Review Completed | 6/7/2024 | CHARMIE HUYNH |
| Plan Check Approved | 7/17/2024 | ANDREW SANTIAGO |
| Issued | 8/19/2024 | APPLICANT |
| OK for CofC | 2/3/2025 | DARRYL ARNOLD |
| CofC Issued | 2/3/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/19/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2024 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/2/2024 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 10/2/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/2/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/11/2024 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/16/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 10/22/2024 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/22/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 2/3/2025 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | DARRYL ARNOLD |