709 E BROADWAY 2 & 3 90291
Certificate Information: 709 E BROADWAY 2 & 3 90291
- Application / Permit
- 24016-10000-17057
- Plan Check / Job No.
- B24LA09861
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- Fire Damage Repairs at Condominium Units "COMPLY WITH DEPARTMENT ORDER effective date 03/21/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/14/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/16/2025
Permit Application Status History
| Submitted | 5/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/2/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 6/6/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/13/2024 | DANIEL ABRAMYAN |
| Issued | 6/14/2024 | APPLICANT |
| Permit Finaled | 6/16/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| Coastal Zone | Cleared | 6/11/2024 | NOAH MCCOY |
Contact Information
| Contractor | Reliance Restoration & Construction; Lic. No.: 1095711-B | , |
| Engineer | Yaghi,, Shucri Ibrahim; Lic. No.: NA43205 | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 8/13/2024 | Partial Approval | GRANT WOODS |
| Wood Frame | 8/13/2024 | Not Ready for Inspection | GRANT WOODS |
| Insulation | 8/15/2024 | Approved | GRANT WOODS |
| Special/Order Compliance | 8/16/2024 | Corrections Issued | GRANT WOODS |
| Interior/Exterior Lathing | 8/30/2024 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 8/30/2024 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Partial Approval | FARHAD DADBIN |
| Final | 10/18/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 10/18/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Drywall Nailing | 11/1/2024 | Approved | FARHAD DADBIN |
| Final | 5/19/2025 | No Access for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 5/19/2025 | No Access for Inspection | FARHAD DADBIN |
| Final | 6/16/2025 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 6/16/2025 | Approved | FARHAD DADBIN |