211 W ELM CT PH44 90067
Certificate Information: 211 W ELM CT PH44 90067
- Application / Permit
- 24016-10000-16973
- Plan Check / Job No.
- B24LA09793
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- TENANT IMPROVEMENT OF PENTHOUSE 44 AT CENTURY PLAZA, NORTH TOWER.
- Permit Issued
- Issued on 10/24/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/29/2026
Permit Application Status History
| Submitted | 5/23/2024 | APPLICANT |
| Assigned to Zoning Architect | 5/30/2024 | ERIC ROMERO |
| Assigned to Plan Check Engineer | 6/6/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 6/14/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/18/2024 | RODOLFO ARIAS |
| Plan Check Approved | 10/23/2024 | SERGIO GUTIERREZ |
| Issued | 10/24/2024 | APPLICANT |
| Permit Finaled | 1/28/2026 | DERRICK SPENCER |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/24/2024 | HISASHI KOBAYAKAWA |
| Tenant Habitability Plan | Cleared | 6/24/2024 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | HISASHI KOBAYAKAWA |
| Fire Marshal Fire Life Safety | Cleared | 7/18/2024 | PEJMAN NOORI |
| Green Code | Cleared | 9/26/2024 | Rosendo Medina |
| Green Code | Cleared | 9/26/2024 | SERGIO GUTIERREZ |
| DAS Clearance | Cleared | 10/1/2024 | Rosendo Medina |
| DAS Clearance | Cleared | 10/1/2024 | SERGIO GUTIERREZ |
| Public Swimming Pool approval | Cleared | 10/8/2024 | LACDHS APPROVED |
| Zoning Plan Check | Cleared | 10/9/2024 | ERIC ROMERO |
Contact Information
| Architect | Abramson,, Trevor David; Lic. No.: NA17597 | , |
| Architect | Abramson,, Trevor David; Lic. No.: NA17597 | , |
| Contractor | Brodin Design Build Inc; Lic. No.: 935646-B | , |
| Engineer | Khachatoorian,, Asbed; Lic. No.: NA39408 | , |
| Engineer | Labib,, Youhanna T.; Lic. No.: NA4549 | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/12/2025 | Partial Approval | RICARDO ROBLES |
| Final | 10/15/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 10/15/2025 | Not Ready for Inspection | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 10/15/2025 | Approved | DERRICK SPENCER |
| Final | 1/28/2026 | Permit Finaled | DERRICK SPENCER |
| Green Building Final | 1/28/2026 | Approved | DERRICK SPENCER |