8043-8045 N NEWCASTLE AVE 91335

Certificate Information: 8043-8045 N NEWCASTLE AVE 91335

Application / Permit
24016-10000-16962
Plan Check / Job No.
B24LA09784
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 6/14/2024
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2024 APPLICANT
Assigned to Plan Check Engineer 5/29/2024 GIOVANNY CHAVEZ
Corrections Issued 5/30/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 6/11/2024 GIOVANNY CHAVEZ
Plan Check Approved 6/13/2024 GIOVANNY CHAVEZ
Issued 6/14/2024 APPLICANT
CofO in Progress 7/8/2026 JUAN ALVARADO
Permit Finaled 7/9/2026 JOHN JANSON
Permit Finaled 7/9/2026 JOHN JANSON
CofO Issued 7/9/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/4/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/4/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/4/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/28/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 6/28/2024 Partial Approval ARUTYUN MADATYAN
Sewer 6/28/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/19/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 7/19/2024 Approved JEFFREY BULL
Green Building Rough 7/19/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 7/19/2024 Approved JEFFREY BULL
Insulation 7/29/2024 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 7/29/2024 Not Ready for Inspection JEFFREY BULL
Shower Pan 7/29/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 8/5/2024 Approved TROY SANDERS
Insulation 8/7/2024 Approved JEFFREY PARD
Drywall Nailing 8/12/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 9/17/2024 Approved JEFFREY BULL
Final 9/17/2024 Corrections Issued JEFFREY BULL
Green Building Final 9/17/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 9/17/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 9/17/2024 Approved JEFFREY BULL
ELECTRICAL-Final 7/8/2026 Approved JUAN ALVARADO
Final 7/8/2026 OK to Issue CofO JUAN ALVARADO
Green Building Final 7/8/2026 Approved JUAN ALVARADO
HVAC-Final 7/8/2026 Approved JUAN ALVARADO
PLUMBING-Final 7/8/2026 Approved JUAN ALVARADO