4904-4904 1/2 E LINCOLN AVE 90042
Certificate Information: 4904-4904 1/2 E LINCOLN AVE 90042
- Application / Permit
- 24016-10000-16950
- Plan Check / Job No.
- B24LA09779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF (E) 1-story SFD INTO 663 SQ FT ADU PER STATE LAW, NO STRUCTURAL WORK. R3 occupancy SEE COMMENT
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | MINA HABILI |
| Corrections Issued | 5/26/2024 | MINA HABILI |
| Building Plans Picked Up | 5/29/2024 | APPLICANT |
| Issued | 6/10/2024 | APPLICANT |
| CofO in Progress | 12/20/2024 | LILIANA PORTILLO |
| Permit Finaled | 1/14/2025 | DEROLD HAUFF |
| Permit Finaled | 1/14/2025 | DEROLD HAUFF |
| CofO Issued | 1/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 6/2/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Pre-Inspection | 7/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 7/10/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/25/2024 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 7/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/7/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/10/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/10/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/10/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/27/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 12/19/2024 | OK to Issue CofO | LILIANA PORTILLO |