3723 S DEGNAN BLVD 90018

Certificate Information: 3723 S DEGNAN BLVD 90018

Application / Permit
24016-10000-16872
Plan Check / Job No.
B24LA09738
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 12/30/2024
Issuing Office
Current Status
CofO Issued on 7/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 ISIS ARGUETA
Corrections Issued 6/1/2024 ISIS ARGUETA
Applicant returned to address corrections 10/30/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 11/20/2024 ISIS ARGUETA
Applicant returned to address corrections 12/11/2024 KAMYAR EMAMI
Plan Check Approved 12/18/2024 KAMYAR EMAMI
Issued 12/30/2024 APPLICANT
CofO in Progress 7/8/2025 LUIS CASTRO
CofO Issued 7/9/2025 DEROLD HAUFF
Permit Finaled 7/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/8/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/8/2024 JEANIE LAM
Sewer availability Cleared 8/8/2024 JEANIE LAM
Construction near power lines Cleared 11/13/2024 RIDWAN HARDY

Contact Information

Contractor Fs-Design And Construction; Lic. No.: 1096835-B       ,
Engineer Contreras,, Humberto; Lic. No.: C83240 10614 PARISE DR      WHITTIER, CA 90604

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/14/2025 Approved LUIS CASTRO
PLUMBING-Rough 1/31/2025 Partial Approval LUIS CASTRO
Sewer 1/31/2025 Approved LUIS CASTRO
Underground Mechanical 1/31/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 2/20/2025 Approved LUIS CASTRO
HVAC-Rough 2/20/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 2/20/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 2/27/2025 Partial Approval ALEX COLIN
Shower Pan 2/27/2025 Approved ALEX COLIN
Insulation 3/11/2025 Approved LUIS CASTRO
Wood Frame 3/11/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved LUIS CASTRO
HVAC-Rough 3/18/2025 Approved LUIS CASTRO
Underground Mechanical 3/18/2025 Approved LUIS CASTRO
Drywall Nailing 3/24/2025 Approved LUIS CASTRO
Green Building Rough 3/24/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 3/24/2025 Not Ready for Inspection LUIS CASTRO
Interior/Exterior Lathing 4/3/2025 No Access for Inspection ARTHUR NEGRETE
PLUMBING-Final 6/3/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 6/20/2025 Approved LUIS CASTRO
Final 6/20/2025 Corrections Issued LUIS CASTRO
Green Building Final 6/20/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 6/20/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Ready LUIS CASTRO
Final 7/3/2025 OK to Issue CofO LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved LUIS CASTRO