341 N GENESEE AVE 90036
Certificate Information: 341 N GENESEE AVE 90036
- Application / Permit
- 24016-10000-16753
- Plan Check / Job No.
- B24LA09659
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED INTERIOR REMODEL OF EXISTING 2-STORY 4 UNITS APARTMENT 1. PROPOSED INTERIOR REMODEL & RELOCATION OF EXISTING 4 KITCHENS. 2. REMODEL OF EXISTING 4 BATHROOMS. 3. ADDITION OF 4 BATHROOMS AND 4 POWDER ROOM. 4. REMOVE EXISTING STAIRCASE AND BUILD NEW WALK-IN CLOSET
- Permit Issued
- Issued on 8/30/2024
- Issuing Office
- Current Status
- Issued on 8/30/2024
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Zoning Architect | 5/30/2024 | NEVRIK NAVASARTIAN |
| Assigned to Plan Check Engineer | 6/6/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 6/17/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/24/2024 | GARO TELMI |
| Plan Check Approved | 8/27/2024 | ARSALAN SHABESTARI |
| Issued | 8/30/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/26/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2024 | AMBER CAMPBELL |
| CPC | Cleared | 7/10/2024 | YINGSHI HUANG |
| Tenant Habitability Plan | Cleared | 7/15/2024 | RICARDO BOHORQUEZ |
| HPOZ | Cleared | 7/24/2024 | RAFAEL FONTES |
| DAS Clearance | Cleared | 8/8/2024 | Kelvin Chuong |
| Zoning Plan Check | Cleared | 8/13/2024 | NEVRIK NAVASARTIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: NA74761 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/23/2024 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 11/13/2024 | Partial Approval | MARTIN TAVITIAN |
| Pre-Inspection | 11/18/2024 | Approved | MARTIN TAVITIAN |
| Wood Frame | 7/14/2025 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Wood Frame | 7/18/2025 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 7/24/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 8/7/2025 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 8/11/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 8/13/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 12/1/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |