101 S SAN PEDRO ST 90012
Certificate Information: 101 S SAN PEDRO ST 90012
- Application / Permit
- 24016-10000-16498
- Plan Check / Job No.
- B24LA09510
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Book Store - new
- Work Description
- ePlan Interior TI: new nonbearing walls, new suspended ceiling, and floor finishes. Combine 5 commercial space (bank, restaurant, and 3 retail stores) to create a new book store.
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Current Status
- Issued on 5/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 6/3/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 6/7/2024 | TU HUA |
| Applicant returned to address corrections | 8/12/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 2/5/2025 | MARCELA FRANQUEZ |
| Assigned to Zoning Architect | 2/5/2025 | BENNY WONG |
| Plan Check Approved | 4/15/2025 | MARCELA FRANQUEZ |
| Issued | 5/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/15/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2024 | CHRISTINA BRACO |
| Miscellaneous | Cleared | 8/16/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 8/16/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 8/16/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 8/16/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 8/16/2024 | MAYELA VILLA |
| Miscellaneous | Cleared | 8/16/2024 | MAYELA VILLA |
| Supp. Use District POD/CDO/TDO | Cleared | 8/16/2024 | SOPHIA KIM |
| "D" conditions | Cleared | 8/29/2024 | YINGSHI HUANG |
| "Q" conditions | Cleared | 8/29/2024 | YINGSHI HUANG |
| Fire Marshal Fire Life Safety | Cleared | 10/23/2024 | ANDREW KO |
| Trees in Parkway | Cleared | 10/28/2024 | ADALBERTO VERA |
| Green Code | Cleared | 11/8/2024 | MICHAEL MARTINEZ |
| CPC | Cleared | 2/12/2025 | DALIA MOKAYED |
| CPC | Cleared | 2/12/2025 | DALIA MOKAYED |
| CPC | Cleared | 2/12/2025 | DALIA MOKAYED |
| CPC | Cleared | 2/12/2025 | DALIA MOKAYED |
| CPC | Cleared | 2/12/2025 | DALIA MOKAYED |
| Miscellaneous | Cleared | 2/12/2025 | DALIA MOKAYED |
| Miscellaneous | Cleared | 2/12/2025 | DALIA MOKAYED |
| ZA Case | Cleared | 2/12/2025 | DALIA MOKAYED |
| Zoning Plan Check | Cleared | 2/28/2025 | BENNY WONG |
| DAS Clearance | Cleared | 3/25/2025 | Cristina Salazar |
Contact Information
| Architect | Tamaoki,, Koichi; Lic. No.: C17879 | 8222 KINGHURST RD SAN GABRIEL, CA 91775 |
| Contractor | Sora Concept Llc; Lic. No.: 1128296-B | 228 E LIVE OAK AVE SUITE 116 ARCADIA,, CA 91006 |
| Engineer | Chen,, Wei-Chih; Lic. No.: S5150 | 1732 DATE AVE TORRANCE, CA 90503 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/11/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 11/14/2025 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 12/15/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 1/6/2026 | Partial Approval | PAUL BAZERKANIAN |
| Green Building Rough | 1/6/2026 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 1/28/2026 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 2/3/2026 | Approved | LARRY ARNICK |
| T-Bar Ceiling | 2/10/2026 | Partial Approval | REGINA MENDEZ |
| Drywall Nailing | 2/13/2026 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 2/13/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| Final | 6/12/2026 | Partial Approval | PAUL BAZERKANIAN |
| Green Building Final | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| Green Building Rough | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| METHANE-Final | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| METHANE-Rough | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| Reinforced Concrete Frame | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2026 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 6/12/2026 | Approved | PAUL BAZERKANIAN |
| Wood Frame | 6/12/2026 | Approved | PAUL BAZERKANIAN |