3111-3113 S OAKHURST AVE 90034
Certificate Information: 3111-3113 S OAKHURST AVE 90034
- Application / Permit
- 24016-10000-16468
- Plan Check / Job No.
- B24LA09483
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK TO BE DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/1/2024
- Issuing Office
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | MADISON ODELL |
| Corrections Issued | 5/25/2024 | MADISON ODELL |
| Applicant returned to address corrections | 6/20/2024 | MADISON ODELL |
| Plan Check Approved | 6/28/2024 | MADISON O'DELL |
| Issued | 7/1/2024 | APPLICANT |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
| CofO Issued | 12/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2024 | DARIN LAM |
| Sewer availability | Cleared | 5/29/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 5/31/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 6/17/2024 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Contractor | Quality First Builders Inc; Lic. No.: 990316-B | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 7/16/2024 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 7/16/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 7/18/2024 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 7/18/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 7/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/30/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 7/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 7/30/2024 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/30/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 8/1/2024 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 8/1/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 8/1/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/5/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 8/5/2024 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 8/5/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 8/5/2024 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/8/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 8/8/2024 | Approved | KIRK SANDERS |
| Green Building Rough | 8/8/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 8/8/2024 | Approved | KIRK SANDERS |
| Insulation | 8/8/2024 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 8/8/2024 | Partial Approval | KIRK SANDERS |
| Special/Order Compliance | 8/8/2024 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 8/13/2024 | Approved | DANIEL VERA |
| Insulation | 8/13/2024 | Partial Approval | DANIEL VERA |
| Shower Pan | 8/13/2024 | Approved | DANIEL VERA |
| Special/Order Compliance | 8/15/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 8/20/2024 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Not Ready | ASHLEY THOMPSON |
| Final | 11/20/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 11/25/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 11/25/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 11/25/2024 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 11/25/2024 | Partial Approval | REGINA MENDEZ |
| Final | 11/27/2024 | Conditional Approval | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/27/2024 | SGSOV Approved | ASHLEY THOMPSON |