780-782 N LATIMER ROAD 90402
Certificate Information: 780-782 N LATIMER ROAD 90402
- Application / Permit
- 24016-10000-16358
- Plan Check / Job No.
- B24LA09408
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- **ePlan**(E) Garage conversion to a 548 sf ADU per CA Govt. Code 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 10/1/2024
- Issuing Office
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | EDWIN ESPIN |
| Corrections Issued | 5/28/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 6/14/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 9/13/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 9/20/2024 | ALFREDO JARA |
| Plan Check Approved | 9/24/2024 | ALFREDO JARA |
| Issued | 10/1/2024 | APPLICANT |
| CofO in Progress | 5/7/2025 | ARAM AVEDISIAN |
| No Progress | 7/23/2025 | KENNETH NAGLE |
| CofO in Progress | 7/23/2025 | KENNETH NAGLE |
| Permit Finaled | 12/4/2025 | RICHARD STEINBACH |
| CofO Issued | 12/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2024 | DARIN LAM |
| ZA Case | Cleared | 6/24/2024 | MATHEW QUAN |
| Grading Pre-Inspection | Cleared | 9/13/2024 | ALFREDO JARA |
| Private sewage disp. approval | Cleared | 9/18/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Silverlining Interiors Inc; Lic. No.: 1083237-B | 163 PASEO DE CONCHA #14 REDONDO BEACH,, CA 90277 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/17/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 12/2/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 12/2/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 12/2/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/9/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 3/28/2025 | Corrections Issued | HERBERT GIRON |
| Final | 3/28/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 3/28/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 3/28/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 3/28/2025 | Partial Approval | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 3/28/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/7/2025 | Approved | ARAM AVEDISIAN |
| Final | 5/7/2025 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 5/7/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 5/7/2025 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/7/2025 | Approved | ARAM AVEDISIAN |