11016 W WRIGHTWOOD PL 91604
Certificate Information: 11016 W WRIGHTWOOD PL 91604
- Application / Permit
- 24016-10000-16242
- Plan Check / Job No.
- B24LA09340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | JOHNPAUL ISIP |
| Corrections Issued | 5/24/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 10/18/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 12/3/2024 | JOHNPAUL ISIP |
| Issued | 12/3/2024 | APPLICANT |
| CofO in Progress | 5/1/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 5/12/2025 | RUBEN SALAS |
| CofO Issued | 5/12/2025 | RUBEN SALAS |
| Permit Finaled | 5/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/31/2024 | VASIL MIHALEV |
| Address approval | Cleared | 6/1/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/1/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 6/1/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | TAL SHEMEN |
| Specific Plan | Cleared | 10/17/2024 | TIFFANY CORRALES |
Contact Information
| Contractor | Hi-Tech Builders Inc; Lic. No.: 957111-B | 5435 BALBOA BLVD STE 200 ENCINO, CA 91316 |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/13/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/24/2024 | Not Ready for Inspection | ROBERT GOLD |
| Underground Mechanical | 12/24/2024 | Corrections Issued | ROBERT GOLD |
| Footing/Foundation/Slab | 12/31/2024 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 12/31/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/3/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/13/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/13/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/13/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 1/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 1/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/22/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 1/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 1/22/2025 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 1/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 1/28/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 2/10/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Insulation | 2/10/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 2/10/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/10/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 2/13/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/13/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Insulation | 2/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 2/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/23/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 4/23/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/23/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/29/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 4/29/2025 | Approved | CHRISTOPHE COCHRAN |