9800 S HARVARD BLVD 90047

Certificate Information: 9800 S HARVARD BLVD 90047

Application / Permit
24016-10000-16093
Plan Check / Job No.
B24LA09222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR RENOVATION (ENCLOSE AREA)
Permit Issued
Issued on 6/3/2024
Issuing Office
Valley
Current Status
Permit Finaled on 5/6/2025

Permit Application Status History

Submitted 5/15/2024 APPLICANT
Assigned to Plan Check Engineer 5/15/2024 JOHN MESIAS
Plan Check Approved 5/15/2024 JOHN MESIAS
Issued 6/3/2024 APPLICANT
Permit Finaled 5/2/2025 WAYNE REGESTER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Eco Construction Management Inc; Lic. No.: 1105333-B 6820 LA TIJERA BLVD STE 117      LOS ANGELES, CA 90045

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/29/2024 Conditional Approval JOSE MACIAS
Deputy Drilled-In Anchors 9/3/2024 No Access for Inspection AMIR NAZARIAN
Footing/Foundation/Slab 9/25/2024 Corrections Issued AMIR NAZARIAN
Piling/Pier/Caisson 9/25/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 9/30/2024 Approved AMIR NAZARIAN
Piling/Pier/Caisson 9/30/2024 Approved AMIR NAZARIAN
Service/Power Release 11/6/2024 Corrections Issued AMIR NAZARIAN
Wood Frame 11/27/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 12/11/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 12/11/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 12/11/2024 Not Ready for Inspection AMIR NAZARIAN
Interior/Exterior Lathing 12/11/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 12/11/2024 Not Ready for Inspection AMIR NAZARIAN
Rough-Elec/Plmb/HVAC 12/11/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 12/12/2024 Corrections Issued AMIR NAZARIAN
Deputy Drilled-In Anchors 12/12/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 12/12/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 12/12/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 12/12/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 12/12/2024 Approved AMIR NAZARIAN
Rough-Elec/Plmb/HVAC 12/12/2024 Not Ready for Inspection AMIR NAZARIAN
Wood Frame 12/12/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 1/15/2025 Approved BARRY HACHE
Wood Frame 1/15/2025 Corrections Issued BARRY HACHE
Deputy Wood Construction 1/16/2025 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 1/21/2025 Approved MICHAEL LEWIS
Insulation 1/21/2025 Approved MICHAEL LEWIS
Wood Frame 1/21/2025 Approved MICHAEL LEWIS
Drywall Nailing 1/24/2025 Approved ANTHONY RAMOS
Final 5/2/2025 Permit Finaled WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved WAYNE REGESTER
Smoke Detectors 5/2/2025 Approved WAYNE REGESTER