1501-1503 S SELBY AVE 90024
Certificate Information: 1501-1503 S SELBY AVE 90024
- Application / Permit
- 24016-10000-16081
- Plan Check / Job No.
- B24LA09204
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Convert portion of (E) SFD into a 1442 sf Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A) Remodel (E( Single family dwelling.
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | EDWIN ESPIN |
| Corrections Issued | 5/28/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/24/2024 | ALFREDO JARA |
| Plan Check Approved | 8/14/2024 | ALFREDO JARA |
| No Progress | 8/14/2024 | ALFREDO JARA |
| Plan Check Approved | 8/14/2024 | ALFREDO JARA |
| No Progress | 8/14/2024 | ALFREDO JARA |
| Plan Check Approved | 8/14/2024 | ALFREDO JARA |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 7/1/2025 | MICHAEL PELHAM |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/23/2024 | DARIN LAM |
| Specific Plan | Cleared | 7/25/2024 | RICHARD WOO |
| "Q" conditions | Cleared | 8/6/2024 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2024 | DARIN LAM |
| Specific Plan | Cleared | 8/12/2024 | JACKSON OLSON |
Contact Information
| Contractor | Young & Associates Construction Services Inc; Lic. No.: 1071533-B | , |
| Engineer | Chikhale,, Jonathan; Lic. No.: C78893 | 2820 MILITARY AVENUE LOS ANGELES, CA 90064 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/24/2024 | Corrections Issued | KIRK SANDERS |
| Deputy Drilled-In Anchors | 9/27/2024 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 11/1/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/10/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 1/10/2025 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 1/10/2025 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 1/10/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 1/17/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 1/17/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 2/5/2025 | Corrections Issued | KIRK SANDERS |
| METHANE-Rough | 2/5/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/11/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 2/11/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 2/14/2025 | Approved | KIRK SANDERS |
| HVAC-Rough | 2/20/2025 | Corrections Issued | KIRK SANDERS |
| Insulation | 2/20/2025 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 2/24/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 3/7/2025 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 3/19/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/24/2025 | Partial Approval | KIRK SANDERS |
| Insulation | 3/24/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/1/2025 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 5/28/2025 | Partial Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/25/2025 | Corrections Issued | KIRK SANDERS |
| Final | 6/25/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 6/25/2025 | Approved | KIRK SANDERS |
| Final | 6/30/2025 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 6/30/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/1/2025 | Approved | MICHAEL PELHAM |
| Final | 7/1/2025 | OK to Issue CofO | MICHAEL PELHAM |