9038 W HARGIS ST 90034

Certificate Information: 9038 W HARGIS ST 90034

Application / Permit
24016-10000-15894
Plan Check / Job No.
B24LA09073
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 20'-0" X 20'-1" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
Permit Issued
Issued on 6/26/2024
Issuing Office
Current Status
CofO Issued on 11/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/20/2024 SERGIO MUNIZ
Corrections Issued 5/21/2024 SERGIO MUNIZ
Plan Check Approved 6/6/2024 DANIEL ABRAMYAN
Issued 6/26/2024 APPLICANT
CofO in Progress 11/7/2024 MEL KHACHATOURIAN
Permit Finaled 11/12/2024 RICHARD STEINBACH
CofO Issued 11/12/2024 RICHARD STEINBACH
Permit Finaled 11/12/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/29/2024 VASIL MIHALEV
Address approval Cleared 6/4/2024 CHRISTINA BRACO
Sewer availability Cleared 6/4/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 6/5/2024 CHRISTINA BRACO

Contact Information

Contractor Gabor Design Group Inc The; Lic. No.: 842370-B       ,
Engineer Villanueva,, Vernon Nipal; Lic. No.: C74117 500 E CARSON PLAZA DR, SUITE 217      CARSON, CA 90746

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/16/2024 Corrections Issued KIRK SANDERS
Pre-Inspection 7/16/2024 Partial Inspection KIRK SANDERS
Underground Mechanical 7/16/2024 Partial Approval KIRK SANDERS
Deputy Drilled-In Anchors 7/19/2024 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 7/19/2024 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 7/26/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 8/19/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 8/19/2024 Partial Approval KIRK SANDERS
Wood Frame 8/19/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 8/23/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 8/23/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/23/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/23/2024 Approved JESUS RODRIGUEZ
Shower Pan 8/23/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/28/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 8/28/2024 Approved MEL KHACHATOURIAN
Green Building Rough 8/28/2024 Approved MEL KHACHATOURIAN
Insulation 8/28/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/28/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 9/4/2024 Approved REGINA MENDEZ
Final 10/29/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 10/29/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 10/29/2024 Approved ARAM AVEDISIAN
Final 11/5/2024 OK to Issue CofO MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved MEL KHACHATOURIAN