67 S BEVERLY PARK CT 90210
Certificate Information: 67 S BEVERLY PARK CT 90210
- Application / Permit
- 24016-10000-15864
- Plan Check / Job No.
- B24LA09047
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INSTALL (N) ELEVATOR IN (E) 2-STORY SFD W/ (E) BASEMENT AND REMODEL TO PORTION OF THE SFD (KITCHEN, FAMILY ROOM, MASTER BATH BEDROOM, LIBRARY)
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- Issued on 6/28/2024
Permit Application Status History
| Submitted | 5/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | KHEDER ALRAZAA |
| Corrections Issued | 6/5/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 6/12/2024 | KEN GILL |
| Building Plans Picked Up | 6/13/2024 | APPLICANT |
| Applicant returned to address corrections | 6/24/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 6/28/2024 | KHEDER ALRAZAA |
| Issued | 6/28/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Manion,, Richard M; Lic. No.: C26957 | 11400 WEST OLYMPIC BLVD SUITE 410 LOS ANGELES, CA 90025 |
| Contractor | Holz Richard Inc; Lic. No.: 294504-B | 520 S SEPULVEDA BLVD #407 LOS ANGELES, CA 90049 |
| Engineer | Pond,, Britten Reis; Lic. No.: C71221 | 1024 CROWN HILL DR SIMI VALLEY, CA 93063 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 12/12/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 1/6/2025 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 2/28/2025 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 4/1/2025 | Partial Approval | SEAN HAUPT |
| Structural Steel Frame | 4/14/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/14/2025 | Partial Approval | SEAN HAUPT |
| Light Gage Steel Frame | 5/14/2025 | Partial Approval | SEAN HAUPT |
| Light Gage Steel Frame | 5/20/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 9/5/2025 | Approved | SEAN HAUPT |
| HVAC-Rough | 9/5/2025 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 9/5/2025 | Approved | SEAN HAUPT |
| Pre-Inspection | 4/6/2026 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 5/12/2026 | Partial Approval | CARLOS MATAMOROS |