8601 S LINCOLN BLVD 90045

Certificate Information: 8601 S LINCOLN BLVD 90045

Application / Permit
24016-10000-15837
Plan Check / Job No.
B24LA09030
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
EPLAN THIS PROJECT CONSISTS OF A RENOVATION OF AN EXISTING 18, 600 S.F. LA FITNESS SIGNATURE SPORTS CLUB INTO A CLUB STUDIO FITNESS FACILITY. THE SCOPE OF WORK FOR THIS PROJECT IS A COMPLETE RENOVATION OF ALL FINISHES, MILLWORK, ROOM LAYOUT AND FACILITIES THROUGHOUT. NO CHANGE OF USE, OCCUPANCY, OR PARKING REQUIREMENTS.
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
Permit Finaled on 12/10/2025

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Zoning Architect 6/13/2024 CALEB WONG
Assigned to Plan Check Engineer 6/20/2024 SERGIO SILVA
Corrections Issued 6/28/2024 SERGIO SILVA
Quality Review Completed 7/9/2024 CHIHARU SUZUKI
Applicant returned to address corrections 9/17/2024 SERGIO SILVA
Applicant returned to address corrections 10/3/2024 SERGIO SILVA
Applicant returned to address corrections 10/15/2024 SERGIO SILVA
Applicant returned to address corrections 11/14/2024 SERGIO SILVA
Plan Check Approved 3/5/2025 SERGIO SILVA
Issued 3/10/2025 APPLICANT
Permit Finaled 12/9/2025 DERRICK SPENCER

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 10/8/2024 FIRE DEPARTMENT
DAS Clearance Cleared 11/25/2024 Samuel Gonzalez
Green Code Cleared 12/3/2024 Samuel Gonzalez
Miscellaneous Cleared 2/4/2025 JAZMIN ROQUE
Miscellaneous Cleared 2/4/2025 JAZMIN ROQUE
Zoning Plan Check Cleared 2/6/2025 Samuel Gonzalez

Contact Information

Contractor J Matt Construction Co; Lic. No.: 1095529-B       ,

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2025 Approved MICHAEL PETRUSKO
Light Gage Steel Frame 7/9/2025 Partial Approval MICHAEL PETRUSKO
Insulation 7/14/2025 Partial Approval DANIEL VARNUM
Drywall Nailing 7/23/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 7/23/2025 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 7/25/2025 Partial Approval MICHAEL PETRUSKO
Insulation 7/29/2025 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 7/30/2025 Partial Approval DANIEL VARNUM
Insulation 8/1/2025 Partial Approval DERRICK SPENCER
Drywall Nailing 8/5/2025 Approved VASIL MIHALEV
Drywall Nailing 8/7/2025 Approved VASIL MIHALEV
Light Gage Steel Frame 8/7/2025 Not Ready for Inspection VASIL MIHALEV
Drywall Nailing 8/14/2025 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/14/2025 Partial Approval DERRICK SPENCER
Drywall Nailing 8/19/2025 Partial Approval DERRICK SPENCER
Drywall Nailing 8/22/2025 Partial Approval DERRICK SPENCER
Insulation 8/22/2025 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/22/2025 Partial Approval DERRICK SPENCER
Drywall Nailing 8/28/2025 Partial Approval DERRICK SPENCER
Insulation 8/28/2025 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/28/2025 Partial Approval DERRICK SPENCER
Drywall Nailing 9/15/2025 Approved DERRICK SPENCER
T-Bar Ceiling 10/24/2025 Approved DERRICK SPENCER
T-Bar Ceiling 10/27/2025 Approved VASIL MIHALEV
T-Bar Ceiling 11/5/2025 Approved DERRICK SPENCER
Final 11/20/2025 Not Ready for Inspection DERRICK SPENCER
Green Building Final 11/20/2025 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Approved DERRICK SPENCER
Smoke Detectors 11/20/2025 Approved DERRICK SPENCER
Pre-Inspection 11/24/2025 Approved DERRICK SPENCER
Final 11/26/2025 Not Ready for Inspection DERRICK SPENCER
Posting Pre-Inspection 12/2/2025 Approved DERRICK SPENCER
Posting Pre-Inspection 12/3/2025 Approved DERRICK SPENCER
Special/Order Compliance 12/4/2025 Approved DERRICK SPENCER
Final 12/5/2025 Not Ready for Inspection DERRICK SPENCER
Pre-Inspection 12/8/2025 Not Ready for Inspection DERRICK SPENCER
Final 12/9/2025 Permit Finaled DERRICK SPENCER