1561 W 228TH ST 1-8 90501
Certificate Information: 1561 W 228TH ST 1-8 90501
- Application / Permit
- 24016-10000-15788
- Plan Check / Job No.
- B24LA08995
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) GARAGE INTO ADU
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Zoning Architect | 5/16/2024 | ELAHE MERRIKHI |
| Assigned to Plan Check Engineer | 5/16/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 5/18/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/24/2024 | GARO TELMI |
| Plan Check Approved | 8/21/2024 | ARSALAN SHABESTARI |
| Issued | 8/22/2024 | APPLICANT |
| Permit Finaled | 11/19/2024 | JOEY BUCHANAN |
| CofO Issued | 11/19/2024 | JOEY BUCHANAN |
| Permit Finaled | 11/19/2024 | JOEY BUCHANAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 5/30/2024 | Cristina Salazar |
| Green Code | Cleared | 7/15/2024 | Cristina Salazar |
| "Q" conditions | Cleared | 7/16/2024 | DAVID URITA |
| Address approval | Cleared | 7/25/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 7/25/2024 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2024 | JILVER MAZARIEGOS |
| Zoning Plan Check | Cleared | 8/12/2024 | ELAHE MERRIKHI |
Contact Information
| Contractor | Shine Invest Llc; Lic. No.: 1079290-B | , |
| Contractor | Shine Invest; Lic. No.: 1079290-B | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/4/2024 | Conditional Approval | AMANUEL BERHE |
| Pre-Inspection | 9/9/2024 | Approved | AMANUEL BERHE |
| Footing/Foundation/Slab | 9/18/2024 | Corrections Issued | JOEY BUCHANAN |
| Green Building Rough | 9/24/2024 | Approved | AMANUEL BERHE |
| METHANE-Rough | 9/24/2024 | Approved | AMANUEL BERHE |
| Wood Frame | 9/24/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Wood Frame | 10/3/2024 | Approved | AMANUEL BERHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Conditional Approval | AMANUEL BERHE |
| Drywall Nailing | 10/16/2024 | Approved | AMANUEL BERHE |
| Final | 11/12/2024 | Conditional Approval | JOEY BUCHANAN |
| Green Building Final | 11/12/2024 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 11/12/2024 | Approved | JOEY BUCHANAN |