1544 W 223RD ST 90501

Certificate Information: 1544 W 223RD ST 90501

Application / Permit
24016-10000-15749
Plan Check / Job No.
B24LA08968
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached 1-Story Garage Conversion to ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/16/2025
Issuing Office
Current Status
Issued on 2/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/16/2024 APPLICANT
Assigned to Plan Check Engineer 5/22/2024 DAVID CASTILLO
Corrections Issued 5/23/2024 DAVID CASTILLO
Applicant returned to address corrections 2/5/2025 DAVID CASTILLO
Plan Check Approved 2/12/2025 DAVID CASTILLO
Issued 2/16/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/30/2025 VISHAL MANDALIA
Sewer availability Cleared 1/30/2025 VISHAL MANDALIA
Eng Process Fee Ord 176,300 Cleared 2/2/2025 VISHAL MANDALIA
Roof/Waste drainage to street Cleared 2/2/2025 VISHAL MANDALIA

Contact Information

Contractor Owner-Builder       ,
Engineer Oseguera,, Jorge; Lic. No.: C86337 428 TIBBETTS ST      SANTA PAULA, CA 93060

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/7/2025 Not Ready for Inspection KELLY WARNER
Final 4/7/2025 Not Ready for Inspection KELLY WARNER
Green Building Rough 4/7/2025 Not Ready for Inspection KELLY WARNER
METHANE-Final 4/7/2025 Not Ready for Inspection KELLY WARNER
METHANE-Rough 4/7/2025 Not Ready for Inspection KELLY WARNER
Pre-Inspection 4/7/2025 Approved KELLY WARNER
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Ready KELLY WARNER
Smoke Detectors 4/7/2025 Not Ready for Inspection KELLY WARNER
Footing/Foundation/Slab 4/9/2025 Corrections Issued KELLY WARNER
Footing/Foundation/Slab 6/5/2025 Approved KELLY WARNER
METHANE-Rough 6/5/2025 No Access for Inspection KELLY WARNER
ELECTRICAL-Final 7/31/2025 Approved KELLY WARNER
Drywall Nailing 8/13/2025 Partial Approval KELLY WARNER
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved KELLY WARNER
Insulation 8/13/2025 Approved KELLY WARNER
Green Building Rough 1/21/2026 Approved KELLY WARNER
Sewer 4/14/2026 Approved KELLY WARNER