3736 N PUEBLO AVE 90032

Certificate Information: 3736 N PUEBLO AVE 90032

Application / Permit
24016-10000-15551
Plan Check / Job No.
B24LA08848
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL SINGLE-FAMILY DWELLING WITH REMOVAL OF WALL BETWEEN KITCHEN AND LIVING ROOM, CREATE NEW BEDROOM, BATHROOM, AND LAUNDRY CLOSET, REMOVE AND REPLACE WINDOWS. "COMPLY WITH DEPARTMENT ORDER effective date 03/12/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
Permit Finaled on 4/22/2026

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/17/2024 ALEC MOUSAKHANIAN
Corrections Issued 5/18/2024 ALEC MOUSAKHANIAN
Plan Check Approved 6/1/2024 ALEC MOUSAKHANIAN
Issued 11/21/2024 APPLICANT
Permit Finaled 4/21/2026 DANIEL DELACRUZ

Permit Application Clearance Information

Sewer availability Cleared 5/29/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 5/30/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Final 2/21/2025 Not Ready for Inspection DANIEL DELACRUZ
HVAC-Final 2/21/2025 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Final 2/21/2025 Not Ready for Inspection DANIEL DELACRUZ
ELECTRICAL-Rough 3/24/2025 Partial Inspection DANIEL DELACRUZ
HVAC-Rough 3/24/2025 Partial Inspection DANIEL DELACRUZ
PLUMBING-Rough 3/24/2025 Partial Inspection DANIEL DELACRUZ
BUILDING-Rough-Frame 11/24/2025 Approved DANIEL DELACRUZ
ELECTRICAL-Rough 11/24/2025 Approved DANIEL DELACRUZ
HVAC-Final 11/24/2025 Partial Approval DANIEL DELACRUZ
ELECTRICAL-Final 4/2/2026 Approved DANIEL DELACRUZ
HVAC-Final 4/2/2026 Approved DANIEL DELACRUZ
PLUMBING-Final 4/2/2026 Approved DANIEL DELACRUZ
Final 4/21/2026 Permit Finaled DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Approved DANIEL DELACRUZ
Smoke Detectors 4/21/2026 Approved DANIEL DELACRUZ