4091 S REDWOOD AVE 101 90066
Certificate Information: 4091 S REDWOOD AVE 101 90066
- Application / Permit
- 24016-10000-15446
- Plan Check / Job No.
- B24LA08764
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Convert a portion of an unit #101 into 4 Storage spaces.
- Permit Issued
- Issued on 6/27/2025
- Issuing Office
- Current Status
- Issued on 6/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | JOE VO |
| Assigned to Zoning Architect | 5/23/2024 | NEVRIK NAVASARTIAN |
| Corrections Issued | 5/31/2024 | JOE VO |
| Quality Review Completed | 6/10/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/5/2024 | JOE VO |
| Plan Check Approved | 6/27/2025 | JOE VO |
| Issued | 6/27/2025 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 6/24/2024 | DAVID URITA |
| Miscellaneous | Cleared | 6/24/2024 | DAVID URITA |
| Miscellaneous | Cleared | 6/24/2024 | DAVID URITA |
| DAS Clearance | Cleared | 12/9/2024 | Fernando Flores |
| Fire Marshal Fire Life Safety | Cleared | 5/20/2025 | PEJMAN NOORI |
| Zoning Plan Check | Cleared | 6/23/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Architect | Kudelka,, Phillip Roman; Lic. No.: C19548 | PK ARCHITECTURE 22663 COLLINS ST WOODLAND HILLS, CA 913674433 |
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2025 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 11/13/2025 | Corrections Issued | MICHAEL PETRUSKO |
| Insulation | 11/14/2025 | Approved | DERRICK SPENCER |
| Partition/T-Bar Ceiling | 11/14/2025 | Approved | DERRICK SPENCER |
| Drywall Nailing | 11/18/2025 | Approved | VASIL MIHALEV |
| Final | 2/10/2026 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Reinforced Concrete Frame | 2/10/2026 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 2/10/2026 | Not Ready for Inspection | MICHAEL PETRUSKO |