1902 N BEL-AIR ROAD 90077
Certificate Information: 1902 N BEL-AIR ROAD 90077
- Application / Permit
- 24016-10000-15439
- Plan Check / Job No.
- B24LA08762
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERSION OF (E) 1,056 SF REC ROOM W/ DECK ABOVE INTO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
- Permit Issued
- Issued on 5/28/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/14/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/21/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/23/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/27/2024 | LUISANGEL VALENZUELA |
| Issued | 5/28/2024 | APPLICANT |
| CofO in Progress | 6/16/2025 | STEPHANIE SWANSON |
| Permit Finaled | 7/21/2025 | RICHARD STEINBACH |
| CofO Issued | 7/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 5/14/2024 | LIAM ODONOVAN |
Contact Information
| Architect | Knollmiller,, Jamie Lyn; Lic. No.: NA31366 | , |
| Contractor | Owner-Builder | , |
| Engineer | Rubio,, Ramon; Lic. No.: S6480 | 5842 WARWICK CIRCLE LA PALMA, CA 90623 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/2/2024 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/11/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/16/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 7/22/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Approved | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 7/26/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 9/6/2024 | Conditional Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/10/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 9/10/2024 | Corrections Issued | SEAN HAUPT |
| Deputy Wood Construction | 9/11/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 9/12/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | CHRISTOPHER WILSON |
| Insulation | 10/17/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/17/2024 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 10/25/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/25/2024 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 10/25/2024 | Approved | CHRISTOPHER WILSON |
| Final | 5/30/2025 | Corrections Issued | CARLOS MATAMOROS |
| Final | 6/6/2025 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 6/6/2025 | Approved | CHRISTOPHER WILSON |
| Final | 6/16/2025 | OK to Issue CofO | STEPHANIE SWANSON |