1902 N BEL-AIR ROAD 90077

Certificate Information: 1902 N BEL-AIR ROAD 90077

Application / Permit
24016-10000-15439
Plan Check / Job No.
B24LA08762
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERSION OF (E) 1,056 SF REC ROOM W/ DECK ABOVE INTO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
Permit Issued
Issued on 5/28/2024
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2024 APPLICANT
Assigned to Plan Check Engineer 5/13/2024 LUISANGEL VALENZUELA
Corrections Issued 5/14/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/21/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/23/2024 LUISANGEL VALENZUELA
Plan Check Approved 5/27/2024 LUISANGEL VALENZUELA
Issued 5/28/2024 APPLICANT
CofO in Progress 6/16/2025 STEPHANIE SWANSON
Permit Finaled 7/21/2025 RICHARD STEINBACH
CofO Issued 7/21/2025 RICHARD STEINBACH
Permit Finaled 7/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/14/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 5/14/2024 LIAM ODONOVAN
Sewer availability Cleared 5/14/2024 LIAM ODONOVAN

Contact Information

Architect Knollmiller,, Jamie Lyn; Lic. No.: NA31366       ,
Contractor Owner-Builder       ,
Engineer Rubio,, Ramon; Lic. No.: S6480 5842 WARWICK CIRCLE      LA PALMA, CA 90623

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/2/2024 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/11/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 7/16/2024 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 7/22/2024 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/24/2024 Approved CHRISTOPHER WILSON
Deputy Drilled-In Anchors 7/26/2024 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 9/6/2024 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/10/2024 Approved SEAN HAUPT
HVAC-Rough 9/10/2024 Corrections Issued SEAN HAUPT
Deputy Wood Construction 9/11/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Approved STEPHANIE SWANSON
HVAC-Rough 9/12/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/17/2024 Approved CHRISTOPHER WILSON
Insulation 10/17/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 10/17/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/25/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 10/25/2024 Approved CHRISTOPHER WILSON
Shower Pan 10/25/2024 Approved CHRISTOPHER WILSON
Final 5/30/2025 Corrections Issued CARLOS MATAMOROS
Final 6/6/2025 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 6/6/2025 Approved CHRISTOPHER WILSON
Final 6/16/2025 OK to Issue CofO STEPHANIE SWANSON