3001 W 75TH ST 90043

Certificate Information: 3001 W 75TH ST 90043

Application / Permit
24016-10000-15360
Plan Check / Job No.
B24LA08709
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING SINGLE FAMILY DWELLING RELOCATE KITCHEN TO CREATE THIRD BEDROOM, ADDITION OF SECOND BATHROOM AT EXISTING CLOSET, NEW LAUNDRY AT EXISTING HALLWAY, COMPLETE REMODEL OF EXISTING BATHROOM AND NEW KITCHEN AT EXISTING DINING AREA - PER WFPP
Permit Issued
Issued on 5/20/2024
Issuing Office
Current Status
Permit Finaled on 2/20/2025

Permit Application Status History

Submitted 5/9/2024 APPLICANT
Assigned to Plan Check Engineer 5/10/2024 DANIEL ABRAMYAN
Corrections Issued 5/13/2024 DANIEL ABRAMYAN
Plan Check Approved 5/18/2024 DANIEL ABRAMYAN
Issued 5/20/2024 APPLICANT
Permit Finaled 2/19/2025 MICHAEL LEWIS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/25/2024 Conditional Approval JOSE MACIAS
Deputy Wood Construction 9/9/2024 No Access for Inspection AMIR NAZARIAN
Deputy Drilled-In Anchors 9/11/2024 No Access for Inspection AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Approved AMIR NAZARIAN
Wood Frame 9/11/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 10/16/2024 Not Ready for Inspection AMIR NAZARIAN
Rough-Elec/Plmb/HVAC 10/16/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 10/22/2024 Corrections Issued AMIR NAZARIAN
Rough-Elec/Plmb/HVAC 10/22/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 11/22/2024 Approved AMIR NAZARIAN
Insulation 11/22/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 11/22/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 11/27/2024 Approved ALEX COLIN
Interior/Exterior Lathing 11/27/2024 Approved ALEX COLIN
Shower Pan 12/3/2024 Approved ALEX COLIN
Final 2/10/2025 Partial Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 2/10/2025 Approved JOHN QUINTANILLA
Smoke Detectors 2/10/2025 Approved JOHN QUINTANILLA
Final 2/19/2025 Permit Finaled MICHAEL LEWIS