4100 W DON DIABLO DR 90008
Certificate Information: 4100 W DON DIABLO DR 90008
- Application / Permit
- 24016-10000-15296
- Plan Check / Job No.
- B24LA08657
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Removal of wall seperating kitchen and living room and kitchen remodel.
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/22/2025
Permit Application Status History
| Submitted | 5/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2024 | CAROLEAN BASMA |
| Corrections Issued | 5/14/2024 | CAROLEAN BASMA |
| Plan Check Approved | 5/29/2024 | CAROLEAN BASMA |
| Issued | 5/29/2024 | APPLICANT |
| Permit Finaled | 8/22/2025 | NICHOLAS LOPEZ |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/23/2024 | JONATHAN HOM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/12/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/14/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/16/2024 | Corrections Issued | ANTHONY EGSON |
| Deputy Steel/Welding | 8/19/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/27/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/19/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/19/2024 | Corrections Issued | BARRY HACHE |
| Wood Frame | 11/19/2024 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 12/5/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/5/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 1/3/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/3/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 2/4/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 2/4/2025 | Approved | LUIS CASTRO |
| Final | 8/22/2025 | Permit Finaled | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 8/22/2025 | Approved | NICHOLAS LOPEZ |