1203 N TOWER GROVE DR 90210

Certificate Information: 1203 N TOWER GROVE DR 90210

Application / Permit
24016-10000-14856
Plan Check / Job No.
B24LA08391
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING RECREATION ROOM TO ADU PER STATE LAW, WITH INTERIOR NON-STRUCTURAL REMODEL
Permit Issued
Issued on 9/26/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 MINA HABILI
Corrections Issued 5/11/2024 MINA HABILI
Building Plans Picked Up 5/15/2024 APPLICANT
Plan Check Approved 8/8/2024 NGHI SU
Issued 9/26/2024 APPLICANT
CofO in Progress 11/18/2025 SEAN HAUPT
Permit Finaled 1/6/2026 RICHARD STEINBACH
CofO Issued 1/6/2026 RICHARD STEINBACH
Permit Finaled 1/6/2026 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 5/20/2024 GEORGIA SMITH
ZA Case Cleared 5/20/2024 GEORGIA SMITH
ZA Case Cleared 5/20/2024 GEORGIA SMITH
Address approval Cleared 5/21/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/21/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/21/2024 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 7/26/2024 RUEL COLE

Contact Information

Architect Beltran,, Xavier A; Lic. No.: C34473 3012 FANITA STREET      LOS ANGELES, CA 90026
Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 10/31/2024 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 10/31/2024 Partial Approval SEAN HAUPT
Underground Mechanical 12/5/2024 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 1/24/2025 Approved CARLOS MATAMOROS
Gas Test 1/24/2025 Approved CARLOS MATAMOROS
HVAC-Rough 1/24/2025 Approved CARLOS MATAMOROS
Light Gage Steel Frame 1/24/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/24/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 2/12/2025 Approved SEAN HAUPT
HVAC-Rough 2/12/2025 Approved SEAN HAUPT
Light Gage Steel Frame 2/12/2025 Partial Approval SEAN HAUPT
PLUMBING-Rough 2/12/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/14/2025 Approved SEAN HAUPT
Insulation 3/14/2025 Approved SEAN HAUPT
Light Gage Steel Frame 3/14/2025 Approved SEAN HAUPT
Drywall Nailing 5/2/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 5/19/2025 Partial Approval DANIEL VERA
PLUMBING-Final 10/20/2025 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 10/30/2025 Approved SEAN HAUPT
HVAC-Final 10/30/2025 Approved SEAN HAUPT
PLUMBING-Final 10/30/2025 Approved SEAN HAUPT
Final 11/4/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 11/4/2025 Not Ready for Inspection SEAN HAUPT
Final 11/17/2025 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved SEAN HAUPT
Smoke Detectors 11/17/2025 Approved SEAN HAUPT