15852 W SEPTO ST 91343

Certificate Information: 15852 W SEPTO ST 91343

Application / Permit
24016-10000-14722
Plan Check / Job No.
B24LA08302
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT MAJORITY (330 SF) OF ATTACHED STORAGE SPACE INTO LIVING SPACE FOR EXISTING SINGLE FAMILY DWELLING . PORTION OF ORIGINAL STORAGE AREA TO REMAIN AS STORAGE (35 SF) . EXTERIOR REMODEL TO INCLUDE EXTERIOR WALL INFILL, EXTERIOR OPENINGS, AND NEW SKYLIGHTS . WORK PER ENGINEERED DESIGN .
Permit Issued
Issued on 9/10/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 ADAM HEGAZI
Corrections Issued 5/6/2024 ADAM HEGAZI
Building Plans Picked Up 5/15/2024 APPLICANT
Plan Check Approved 6/10/2024 GEORGE ALVAREZ
Issued 9/10/2024 APPLICANT
CofO in Progress 10/10/2025 NICHOLAS TROWBRIDGE
Permit Finaled 10/23/2025 RUBEN SALAS
CofO Issued 10/23/2025 RUBEN SALAS
Permit Finaled 10/23/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/21/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 5/31/2024 EDGAR ALCARAZ
Sewer availability Cleared 5/31/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/23/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/23/2024 Approved VINCENT HANLEY
PLUMBING-Final 10/23/2024 Partial Approval VINCENT HANLEY
Sewer 10/23/2024 Approved VINCENT HANLEY
Pre-Inspection 10/30/2024 Partial Approval MICHEL ABAJAN
Special/Order Compliance 12/27/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 1/7/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 1/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 1/7/2025 Approved JAVIER RAMOS JR
Pre-Inspection 1/7/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Partial Inspection JAVIER RAMOS JR
HVAC-Rough 1/16/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Approved JAVIER RAMOS JR
HVAC-Rough 1/28/2025 Approved JAVIER RAMOS JR
Insulation 1/28/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/28/2025 Approved JAVIER RAMOS JR
Shower Pan 1/28/2025 Approved JAVIER RAMOS JR
Drywall Nailing 2/4/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 8/25/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/25/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 8/25/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 8/25/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 8/25/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/9/2025 Approved NICHOLAS TROWBRIDGE
Final 9/9/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 9/9/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Final 10/9/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 10/9/2025 Approved NICHOLAS TROWBRIDGE