1720 S WASHINGTON WAY 90291

Certificate Information: 1720 S WASHINGTON WAY 90291

Application / Permit
24016-10000-14697
Plan Check / Job No.
B24LA08285
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel to a one-story single-family dwelling. All work is interior. No change of use, building dimensions, or height. All work done per an engineered design.
Permit Issued
Issued on 10/7/2024
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 2/10/2025

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 DANIEL SMILEY
Plan Check Approved 5/3/2024 DANIEL SMILEY
Issued 10/7/2024 APPLICANT
Permit Finaled 2/10/2025 HERBERT GIRON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Rb Development And Consulting Llc; Lic. No.: 1088873-B 430 TALBERT STREET      PLAYA DEL REY, CA 90293
Engineer Kashe,, Andrew; Lic. No.: C94117 984 SILVERTIP DR      DIAMOND BAR, CA 91765

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/9/2024 Corrections Issued HERBERT GIRON
Special/Order Compliance 10/9/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/21/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 10/21/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/22/2024 Approved HERBERT GIRON
HVAC-Final 10/22/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 10/22/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/23/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/23/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 10/24/2024 Partial Approval HERBERT GIRON
Insulation 10/24/2024 Partial Approval HERBERT GIRON
Drywall Nailing 10/28/2024 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 11/6/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/6/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/15/2024 Approved HERBERT GIRON
PLUMBING-Rough 11/19/2024 Not Ready for Inspection HERBERT GIRON
Special/Order Compliance 11/19/2024 Partial Inspection REGINA MENDEZ
PLUMBING-Rough 11/20/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 11/25/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 11/25/2024 Approved HERBERT GIRON
Shower Pan 11/25/2024 Approved HERBERT GIRON
Wood Frame 12/4/2024 Approved MICHAEL ALLEN
Pre-Inspection 12/27/2024 Approved MICHAEL ALLEN
Final 1/21/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 1/21/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 1/29/2025 Corrections Issued HERBERT GIRON
Final 1/29/2025 Corrections Issued HERBERT GIRON
HVAC-Final 1/29/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/29/2025 Approved HERBERT GIRON
Smoke Detectors 1/29/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/31/2025 Approved HERBERT GIRON
Final 1/31/2025 Corrections Issued HERBERT GIRON
HVAC-Final 1/31/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/31/2025 Approved HERBERT GIRON
Smoke Detectors 1/31/2025 Approved HERBERT GIRON
Final 2/10/2025 Permit Finaled HERBERT GIRON
HVAC-Final 2/10/2025 Approved HERBERT GIRON