11339 W CASHMERE ST 90049

Certificate Information: 11339 W CASHMERE ST 90049

Application / Permit
24016-10000-14571
Plan Check / Job No.
B24LA08206
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EX. GARAGE INTO ATTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C) FOR EXISTING 3-UNIT MULTI-FAMILY.
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
CofO Issued on 12/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2024 APPLICANT
Assigned to Plan Check Engineer 5/8/2024 ROSENDO MEDINA
Corrections Issued 5/8/2024 ROSENDO MEDINA
Plan Check Approved 6/19/2024 ROSENDO MEDINA
Issued 6/28/2024 APPLICANT
CofO in Progress 12/5/2025 CASIMIR BRITTON
Permit Finaled 12/9/2025 DAVID TSAU
CofO Issued 12/9/2025 DAVID TSAU
Permit Finaled 12/9/2025 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 5/11/2024 DARIN LAM
Sewer availability Cleared 5/11/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/15/2024 DARIN LAM
Specific Plan Cleared 5/29/2024 EDUARDO HERMOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/10/2024 No Access for Inspection CASIMIR BRITTON
Green Building Rough 9/10/2024 No Access for Inspection CASIMIR BRITTON
METHANE-Rough 9/10/2024 No Access for Inspection CASIMIR BRITTON
Wood Frame 9/10/2024 No Access for Inspection CASIMIR BRITTON
Excavation/Setback/Form/Re-Bar 3/10/2025 Not Ready for Inspection CASIMIR BRITTON
Footing/Foundation/Slab 3/10/2025 Not Ready for Inspection CASIMIR BRITTON
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved CASIMIR BRITTON
Green Building Rough 4/10/2025 Not Ready for Inspection CASIMIR BRITTON
METHANE-Rough 4/10/2025 Not Ready for Inspection CASIMIR BRITTON
Final 12/5/2025 OK to Issue CofO CASIMIR BRITTON
Green Building Final 12/5/2025 Approved CASIMIR BRITTON
Green Building Rough 12/5/2025 Approved CASIMIR BRITTON
METHANE-Final 12/5/2025 Approved CASIMIR BRITTON
METHANE-Rough 12/5/2025 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 12/5/2025 Approved CASIMIR BRITTON
Wood Frame 12/5/2025 Approved CASIMIR BRITTON