3715 N DIXIE CANYON AVE 91423

Certificate Information: 3715 N DIXIE CANYON AVE 91423

Application / Permit
24016-10000-14549
Plan Check / Job No.
B24LA08191
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan - New second story addition above 1st story portion of existing SFD
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
Issued on 7/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/2/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 MARCELA FRANQUEZ
Corrections Issued 5/11/2024 MARCELA FRANQUEZ
Quality Review Completed 5/16/2024 GARO TELMI
Applicant returned to address corrections 1/23/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 2/12/2025 MARCELA FRANQUEZ
Plan Check Approved 5/7/2025 MARCELA FRANQUEZ
Issued 7/1/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/15/2024 CARLOS RAMIREZ
Watercourse Cleared 10/15/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 11/5/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 2/19/2025 CARLOS RAMIREZ
Sewer availability Cleared 2/19/2025 CARLOS RAMIREZ
Hydrant and Access approval Cleared 4/3/2025 RUEL COLE
Specific Plan Cleared 4/8/2025 TIFFANY CORRALES

Contact Information

Contractor Dream Construction; Lic. No.: 1051776-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/9/2025 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/9/2025 Approved MISAEL ESPARZA
Footing/Foundation/Slab 9/9/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/13/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/13/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/13/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/5/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 12/5/2025 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 12/5/2025 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/11/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/11/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Approved MISAEL ESPARZA
Green Building Rough 12/11/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 12/11/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 12/11/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 12/30/2025 Approved JACK KARGODORIAN
Pre-Inspection 1/8/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/3/2026 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/19/2026 Partial Inspection JAVIER RAMOS JR
Insulation 2/19/2026 Partial Approval JAVIER RAMOS JR
Shower Pan 2/19/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/11/2026 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 3/13/2026 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/13/2026 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 3/18/2026 Approved MISAEL ESPARZA
Green Building Rough 3/18/2026 Approved MISAEL ESPARZA