3715 N DIXIE CANYON AVE 91423
Certificate Information: 3715 N DIXIE CANYON AVE 91423
- Application / Permit
- 24016-10000-14549
- Plan Check / Job No.
- B24LA08191
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan - New second story addition above 1st story portion of existing SFD
- Permit Issued
- Issued on 7/1/2025
- Issuing Office
- Current Status
- Issued on 7/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 5/11/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/16/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/23/2025 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 2/12/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/7/2025 | MARCELA FRANQUEZ |
| Issued | 7/1/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/15/2024 | CARLOS RAMIREZ |
| Watercourse | Cleared | 10/15/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 11/5/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2025 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/19/2025 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 4/3/2025 | RUEL COLE |
| Specific Plan | Cleared | 4/8/2025 | TIFFANY CORRALES |
Contact Information
| Contractor | Dream Construction; Lic. No.: 1051776-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2025 | Conditional Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/9/2025 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/9/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 11/13/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 11/13/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/5/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 12/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/11/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/11/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/30/2025 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 1/8/2026 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/3/2026 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/19/2026 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 2/19/2026 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 2/19/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/11/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 3/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 3/18/2026 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/18/2026 | Approved | MISAEL ESPARZA |