5566 E VIA MARISOL 90042
Certificate Information: 5566 E VIA MARISOL 90042
- Application / Permit
- 24016-10000-14155
- Plan Check / Job No.
- B24LA07937
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INTERIOR RENOVATION OF A RESTROOM STRUCTURE AT HERMON PARK. THIS IS A LOS ANGELES CITY RECREATION AND PARKS OWNED PARK. PROJECT PROPOSES TO RENOVATE TWO MULTI STALL RESTROOMS (MEN'S AND WOMEN'S) INTO TWO SINGLE OCCUPANCY GENDER NEUTRAL RESTROOMS. THERE IS EXISTING ADA PARKING ONSITE, AND PROJECT SCOPE INCLUDES RESTRIPING AND ADDING ACCESSIBLE PARKING SIGNAGE FOR BETTER VISIBILITY.
- Permit Issued
- Issued on 9/27/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/30/2026
Permit Application Status History
| Submitted | 4/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | JOE VO |
| Assigned to Zoning Architect | 5/9/2024 | MELISSA QUINONES |
| Building Plans Picked Up | 5/20/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 6/11/2024 | APPLICANT |
| Corrections Issued | 8/21/2024 | JOE VO |
| Quality Review Completed | 8/22/2024 | JOHN FRANCIA |
| Plan Check Approved | 9/24/2024 | JOE VO |
| Issued | 9/27/2024 | APPLICANT |
| Permit Finaled | 11/6/2025 | JEROME BLACKWOOD |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 5/21/2024 | MELISSA QUINONES |
| DAS Clearance | Cleared | 9/11/2024 | JOE VO |
Contact Information
| Architect | Cheng,, Jasmine; Lic. No.: C41277 | 920 N EL CENTRO #3 LOS ANGELES, CA 90038 |
| Contractor | Houalla Enterprises Ltd; Lic. No.: 597589-B | 2610 AVON ST NEWPORT BEACH, CA 92663 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 2/21/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 3/25/2025 | Corrections Issued | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 6/5/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Corrections Issued | JEROME BLACKWOOD |
| Wood Frame | 6/13/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 7/1/2025 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 7/2/2025 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 7/2/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 7/29/2025 | Approved | JEROME BLACKWOOD |
| Drywall Nailing | 8/19/2025 | Approved | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 9/2/2025 | Partial Approval | JEROME BLACKWOOD |
| Final | 11/6/2025 | Permit Finaled | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 11/6/2025 | Approved | JEROME BLACKWOOD |