Work Description
Convert (E) detached garage into an accessory dwelling unit PER GCS 65852.2(e)(1)(A)).
Permit Issued
Issued on 9/17/2024
Issuing Office
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2024 APPLICANT
Assigned to Plan Check Engineer 4/30/2024 NGHI SU
Corrections Issued 5/1/2024 NGHI SU
Plan Check Approved 9/16/2024 SHANGQIN XIE
Issued 9/17/2024 APPLICANT
CofO in Progress 7/25/2025 ARAM AVEDISIAN
Permit Finaled 7/29/2025 RICHARD STEINBACH
CofO Issued 7/29/2025 RICHARD STEINBACH
Permit Finaled 7/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/7/2024 DARIN LAM
Sewer availability Cleared 5/7/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/28/2024 DARIN LAM
Construction near power lines Cleared 8/21/2024 RIDWAN HARDY
Construction within easement Cleared 8/21/2024 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor U S Home Developers Inc; Lic. No.: 947505-B       ,
Contractor Us Home Developers Inc; Lic. No.: 947505-B       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/13/2025 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/14/2025 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 1/27/2025 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 2/20/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 2/20/2025 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 2/27/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/1/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 4/1/2025 Approved KIRK SANDERS
Footing/Foundation/Slab 4/1/2025 Approved KIRK SANDERS
HVAC-Rough 4/1/2025 Approved KIRK SANDERS
PLUMBING-Rough 4/1/2025 Conditional Approval KIRK SANDERS
Sewer 4/1/2025 Approved KIRK SANDERS
Special/Order Compliance 4/1/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 4/7/2025 Conditional Approval KIRK SANDERS
Interior/Exterior Lathing 4/7/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 4/15/2025 Corrections Issued KIRK SANDERS
Insulation 4/15/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 4/18/2025 Approved SEAN HAUPT
Green Building Rough 4/18/2025 Approved SEAN HAUPT
Drywall Nailing 4/29/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 4/29/2025 Approved KIRK SANDERS
Shower Pan 4/29/2025 Approved KIRK SANDERS
Final 6/30/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 6/30/2025 Approved STEPHANIE SWANSON
Final 7/23/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 7/25/2025 Approved ARAM AVEDISIAN
Final 7/25/2025 OK to Issue CofO ARAM AVEDISIAN