3945 S NORTON AVE 90008
Certificate Information: 3945 S NORTON AVE 90008
- Application / Permit
- 24016-10000-13842
- Plan Check / Job No.
- B24LA07726
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Major remodel to existing S.F.D. Add new uncovered rear deck.
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Current Status
- Permit Finaled on 10/24/2024
Permit Application Status History
| Submitted | 4/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2024 | CAROLEAN BASMA |
| Corrections Issued | 5/2/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 5/16/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 5/20/2024 | CAROLEAN BASMA |
| Plan Check Approved | 5/27/2024 | CAROLEAN BASMA |
| Issued | 5/29/2024 | APPLICANT |
| Permit Finaled | 10/24/2024 | BARRY HACHE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/10/2024 | EDGAR PASCUA |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 5/23/2024 | JESSICA OPINION |
Contact Information
| Contractor | W M Construction Group Inc; Lic. No.: 1104199-B | , |
| Engineer | Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 | 4000 PARK NEWPORT SUITE 303 NEWPORT BEACH, CA 92660 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/11/2024 | Approved | ANTHONY EGSON |
| Wood Frame | 6/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/31/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/31/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 7/31/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/31/2024 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 7/31/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/13/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/13/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 8/13/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 8/15/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 8/15/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/19/2024 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/27/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/30/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/5/2024 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 9/5/2024 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Approved | ANTHONY EGSON |
| Insulation | 9/5/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/12/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 9/12/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/17/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/19/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/23/2024 | Approved | BARRY HACHE |
| HVAC-Final | 10/23/2024 | Approved | BARRY HACHE |
| PLUMBING-Final | 10/23/2024 | Corrections Issued | BARRY HACHE |
| Final | 10/24/2024 | Permit Finaled | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 10/24/2024 | Approved | BARRY HACHE |