- Permit Issued
- Issued on 5/28/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/4/2025
Permit Application Status History
| Submitted | 4/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2024 | EDWIN ESPIN |
| Corrections Issued | 4/26/2024 | EDWIN ESPIN |
| Plan Check Approved | 5/15/2024 | EDWIN ESPIN |
| Issued | 5/28/2024 | APPLICANT |
| Permit Finaled | 9/4/2025 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/30/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 2/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/26/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 3/26/2025 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 3/26/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/26/2025 | Approved | KEVIN SARGSYAN |
| Sewer | 3/26/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 3/26/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/28/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/28/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 3/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 3/28/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/2/2025 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | KEVIN SARGSYAN |
| Wood Frame | 4/11/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 4/17/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/17/2025 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 4/25/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/25/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 7/31/2025 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 7/31/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 7/31/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/20/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 8/20/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 8/20/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 8/20/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 9/4/2025 | Permit Finaled | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 9/4/2025 | Approved | KEVIN SARGSYAN |