3848 1/2 S ALSACE AVE 90008
Certificate Information: 3848 1/2 S ALSACE AVE 90008
- Application / Permit
- 24016-10000-13650
- Plan Check / Job No.
- B24LA07554
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND ADDITION (E) DETACHED GARAGE TO (N) 356 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). (E) ATTACHED 1-CAR GARAGE TO REMAIN. WORK TO BE DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2024 | MADISON ODELL |
| Corrections Issued | 5/3/2024 | MADISON ODELL |
| Applicant returned to address corrections | 5/30/2024 | JAD BASMA |
| Applicant returned to address corrections | 6/4/2024 | JAD BASMA |
| Plan Check Approved | 6/6/2024 | SHANGQIN XIE |
| Issued | 6/7/2024 | APPLICANT |
| CofO in Progress | 2/11/2025 | LUIS CASTRO |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2024 | WALLIE JONG |
| Sewer availability | Cleared | 5/23/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 5/24/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2024 | WALLIE JONG |
Contact Information
| Contractor | Iba Builders Inc; Lic. No.: 1074505-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 6/25/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 7/1/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/5/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/5/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/10/2024 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/15/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/19/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/19/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/16/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/16/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/16/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/28/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/28/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/28/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/4/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/11/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 9/11/2024 | Approved | ANTHONY EGSON |
| Insulation | 9/19/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/19/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/23/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/1/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/4/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/15/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 10/15/2024 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 11/19/2024 | Approved | BARRY HACHE |
| Underground Mechanical | 11/19/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 1/22/2025 | Approved | LUIS CASTRO |
| Final | 1/22/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 1/22/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 1/22/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 1/22/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 1/22/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 1/29/2025 | Approved | LUIS CASTRO |
| Final | 1/29/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 1/29/2025 | Approved | LUIS CASTRO |
| Final | 2/10/2025 | OK to Issue CofO | LUIS CASTRO |