3848 1/2 S ALSACE AVE 90008

Certificate Information: 3848 1/2 S ALSACE AVE 90008

Application / Permit
24016-10000-13650
Plan Check / Job No.
B24LA07554
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AND ADDITION (E) DETACHED GARAGE TO (N) 356 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). (E) ATTACHED 1-CAR GARAGE TO REMAIN. WORK TO BE DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 6/7/2024
Issuing Office
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 MADISON ODELL
Corrections Issued 5/3/2024 MADISON ODELL
Applicant returned to address corrections 5/30/2024 JAD BASMA
Applicant returned to address corrections 6/4/2024 JAD BASMA
Plan Check Approved 6/6/2024 SHANGQIN XIE
Issued 6/7/2024 APPLICANT
CofO in Progress 2/11/2025 LUIS CASTRO
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/23/2024 WALLIE JONG
Sewer availability Cleared 5/23/2024 WALLIE JONG
Grading Pre-Inspection Cleared 5/24/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 5/31/2024 WALLIE JONG

Contact Information

Contractor Iba Builders Inc; Lic. No.: 1074505-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2024 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 6/18/2024 Corrections Issued ANTHONY EGSON
Deputy Drilled-In Anchors 6/25/2024 Approved ANTHONY EGSON
PLUMBING-Rough 7/1/2024 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 7/5/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/5/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/10/2024 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 7/15/2024 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 7/19/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 7/19/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/16/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 8/16/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 8/16/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/16/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 8/28/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/28/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 8/28/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/28/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 9/4/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 9/11/2024 Partial Approval ANTHONY EGSON
Green Building Rough 9/11/2024 Approved ANTHONY EGSON
Insulation 9/19/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/19/2024 Approved ANTHONY EGSON
Drywall Nailing 9/23/2024 Approved ANTHONY EGSON
Drywall Nailing 10/1/2024 Approved ANTHONY EGSON
Drywall Nailing 10/4/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 10/15/2024 Approved ANTHONY EGSON
Shower Pan 10/15/2024 Corrections Issued ANTHONY EGSON
Gas Test 11/19/2024 Approved BARRY HACHE
Underground Mechanical 11/19/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 1/22/2025 Approved LUIS CASTRO
ELECTRICAL-Final 1/22/2025 Approved LUIS CASTRO
Final 1/22/2025 Corrections Issued LUIS CASTRO
Green Building Final 1/22/2025 Approved LUIS CASTRO
HVAC-Final 1/22/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 1/22/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 1/22/2025 Approved LUIS CASTRO
ELECTRICAL-Final 1/29/2025 Approved LUIS CASTRO
Final 1/29/2025 Corrections Issued LUIS CASTRO
HVAC-Final 1/29/2025 Approved LUIS CASTRO
Final 2/10/2025 OK to Issue CofO LUIS CASTRO