4114 N DIVISION ST 90065

Certificate Information: 4114 N DIVISION ST 90065

Application / Permit
24016-10000-13647
Plan Check / Job No.
B24LA07551
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Conversion of an existing 20'-3" x 31'-9" unpermitted structure built prior to Jan 1 2018 to an Accessory Dwelling Unit per GCS 65852.23. TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGH OUT. Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 03/15/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector JONATHAN FRANCHINI at (213)252-3058 of GENERAL ENFORCEMENT CENTRAL. CEIS Case Number is 995939.
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
CofO Issued on 11/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 ADRIANA LOPEZ
Corrections Issued 5/21/2024 ADRIANA LOPEZ
Quality Review Completed 6/5/2024 SINA KHOSRAVI
Applicant returned to address corrections 8/16/2024 ADRIANA LOPEZ
Applicant returned to address corrections 9/30/2024 ADRIANA LOPEZ
Plan Check Approved 10/8/2024 ADRIANA LOPEZ
Issued 10/23/2024 APPLICANT
CofO in Progress 9/2/2025 JACOB SEGURA
Permit Finaled 11/7/2025 DANIEL SANCHEZ
CofO Issued 11/7/2025 DANIEL SANCHEZ
Permit Finaled 11/7/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 6/10/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 6/11/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 6/11/2024 JILVER MAZARIEGOS
Sewer availability Cleared 6/11/2024 JILVER MAZARIEGOS
Specific Plan Cleared 7/3/2024 PABLO ESTRADA
Hydrant and Access approval Cleared 8/10/2024 JOHN CONNEALLY
GPI Written Notices Cleared 9/30/2024 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 9/30/2024 ADRIANA LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chang,, Yeh; Lic. No.: S6868 168 S SIERRA MADRE BLVD 109      PASADENA, CA 91107

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2024 Approved JACOB SEGURA
Pre-Inspection 12/31/2024 Approved JACOB SEGURA
Pre-Inspection 2/25/2025 Approved JACOB SEGURA
Deputy Drilled-In Anchors 3/18/2025 Approved FERMIN RUBIO
Excavation/Setback/Form/Re-Bar 3/18/2025 Corrections Issued FERMIN RUBIO
Footing/Foundation/Slab 3/18/2025 Corrections Issued FERMIN RUBIO
Excavation/Setback/Form/Re-Bar 4/8/2025 Partial Approval JACOB SEGURA
Excavation/Setback/Form/Re-Bar 4/9/2025 Corrections Issued JACOB SEGURA
Footing/Foundation/Slab 4/9/2025 Partial Approval JACOB SEGURA
Deputy Drilled-In Anchors 4/28/2025 No Access for Inspection JACOB SEGURA
Excavation/Setback/Form/Re-Bar 4/29/2025 Approved JACOB SEGURA
Footing/Foundation/Slab 4/29/2025 Approved JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval JACOB SEGURA
Deputy Drilled-In Anchors 5/14/2025 No Access for Inspection JACOB SEGURA
ELECTRICAL-Rough 5/28/2025 Corrections Issued JACOB SEGURA
Excavation/Setback/Form/Re-Bar 5/28/2025 Approved JACOB SEGURA
Footing/Foundation/Slab 5/28/2025 Approved JACOB SEGURA
HVAC-Rough 5/28/2025 Approved JACOB SEGURA
PLUMBING-Rough 5/28/2025 Corrections Issued JACOB SEGURA
Underground Mechanical 5/28/2025 Partial Approval JACOB SEGURA
Verify Sprinkler Sign Off 5/28/2025 Approved JACOB SEGURA
ELECTRICAL-Rough 6/4/2025 Approved JACOB SEGURA
PLUMBING-Rough 6/4/2025 Not Ready for Inspection JACOB SEGURA
Wood Frame 6/4/2025 Corrections Issued JACOB SEGURA
BUILDING-Rough-Frame 6/12/2025 Partial Approval JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Approved FERMIN RUBIO
Wood Frame 6/17/2025 Approved FERMIN RUBIO
Drywall Nailing 6/24/2025 Approved JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Approved JACOB SEGURA
Green Building Rough 6/24/2025 Approved JACOB SEGURA
Insulation 6/24/2025 Approved JACOB SEGURA
Gas Test 7/31/2025 Approved JACOB SEGURA
PLUMBING-Rough 7/31/2025 Approved JACOB SEGURA
BUILDING-Rough-Frame 8/6/2025 Approved JACOB SEGURA
Final 8/6/2025 Corrections Issued JACOB SEGURA
Green Building Final 8/6/2025 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 8/6/2025 SGSOV Approved JACOB SEGURA
Service/Power Release 8/6/2025 Not Required JACOB SEGURA
Smoke Detectors 8/6/2025 Approved JACOB SEGURA
Final 8/12/2025 Conditional Approval JACOB SEGURA
Final 8/14/2025 OK to Issue CofO JACOB SEGURA
ELECTRICAL-Final 9/2/2025 Approved JACOB SEGURA
HVAC-Final 9/2/2025 Approved JACOB SEGURA
PLUMBING-Final 9/2/2025 Approved JACOB SEGURA
Interior/Exterior Lathing 10/6/2025 Approved JACOB SEGURA
Sewer 10/6/2025 Approved JACOB SEGURA
Shower Pan 10/6/2025 Approved JACOB SEGURA
Underground Mechanical 10/6/2025 Approved JACOB SEGURA