446 N CROFT AVE 90048
Certificate Information: 446 N CROFT AVE 90048
- Application / Permit
- 24016-10000-13321
- Plan Check / Job No.
- B24LA05461
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Alteration to (E) 2-story duplex to convert to SFD.
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 5/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 4/24/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 4/30/2024 | RODOLFO ARIAS |
| Plan Check Approved | 8/22/2024 | GEORGE JOLAKIAN |
| Issued | 8/22/2024 | APPLICANT |
| CofO in Progress | 5/23/2025 | JOSE MACIAS |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
| CofO Issued | 5/25/2025 | DEROLD HAUFF |
| Permit Finaled | 5/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/30/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2024 | CELINA MORENO |
| SB8 RUD | Cleared | 7/22/2024 | KEVIN SCHULTZ |
| Tenant Habitability Plan | Cleared | 8/12/2024 | ISMAEL HERNANDEZ |
| Demo/Removal of Rental Units | Cleared | 8/20/2024 | SUSAN LIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/26/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/26/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/26/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/29/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Rough | 8/29/2024 | Approved | WILLIAM SIERRA |
| Deputy Wood Construction | 8/30/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | No Access for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/12/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/11/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 10/11/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/16/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 11/18/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/18/2024 | Approved | JOSE MACIAS |
| Sewer | 11/18/2024 | Approved | JOSE MACIAS |
| Shower Pan | 11/18/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 11/26/2024 | Approved | JOSE MACIAS |
| Insulation | 11/26/2024 | Conditional Approval | JOSE MACIAS |
| Interior/Exterior Lathing | 12/4/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 12/6/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 4/29/2025 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 4/29/2025 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 5/2/2025 | Approved | JOSE MACIAS |
| HVAC-Final | 5/13/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 5/13/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/14/2025 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 5/14/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 5/14/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/15/2025 | Approved | JEFFREY MEAD |
| HVAC-Final | 5/15/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | JOSE MACIAS |
| Final | 5/19/2025 | OK to Issue CofO | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 5/19/2025 | Approved | JOSE MACIAS |