8931 W HARGIS ST 90034

Certificate Information: 8931 W HARGIS ST 90034

Application / Permit
24016-10000-13266
Plan Check / Job No.
B24LA07340
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN "Conversion of an existing 20' x 24' unpermitted structure built prior to Jan 1 2018 to an Accessory Dwelling Unit per GCS 65852.23" ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/31/2025
Issuing Office
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 MADISON ODELL
Corrections Issued 5/3/2024 MADISON ODELL
Applicant returned to address corrections 12/23/2024 ARAMIK SHAHMIRZAIAN
Plan Check Approved 1/8/2025 ARAMIK SHAHMIRZAIAN
Issued 1/31/2025 APPLICANT
CofO in Progress 10/23/2025 EVAN COOPER
Permit Finaled 11/4/2025 RICHARD STEINBACH
CofO Issued 11/4/2025 RICHARD STEINBACH
Permit Finaled 11/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/21/2024 WALLIE JONG
Sewer availability Cleared 5/21/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/28/2024 WALLIE JONG
Construction near power lines Cleared 11/19/2024 RIDWAN HARDY
Construction within easement Cleared 11/19/2024 RIDWAN HARDY

Contact Information

Contractor Bethany Samuel D; Lic. No.: 1089466-B       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/29/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/29/2025 Partial Approval ARAM AVEDISIAN
Sewer 5/29/2025 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 6/2/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 6/20/2025 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 6/20/2025 Corrections Issued EVAN COOPER
HVAC-Rough 6/20/2025 Corrections Issued EVAN COOPER
MERV13>=Rough 6/20/2025 Approved EVAN COOPER
PLUMBING-Rough 6/20/2025 Approved EVAN COOPER
Interior/Exterior Lathing 7/1/2025 Partial Approval ARAM AVEDISIAN
Shower Pan 7/1/2025 Approved ARAM AVEDISIAN
Drywall Nailing 7/8/2025 Approved EVAN COOPER
Insulation 7/8/2025 Approved EVAN COOPER
Interior/Exterior Lathing 7/16/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 10/21/2025 Approved ANDREW NAVE
Final 10/21/2025 Corrections Issued ANDREW NAVE
MERV13>=Final 10/21/2025 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Approved ANDREW NAVE
Smoke Detectors 10/21/2025 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 10/23/2025 Approved EVAN COOPER
Final 10/23/2025 OK to Issue CofO EVAN COOPER
HVAC-Final 10/23/2025 Approved EVAN COOPER
PLUMBING-Final 10/23/2025 Approved EVAN COOPER
Smoke Detectors 10/23/2025 Approved EVAN COOPER