3788 S BRONSON AVE 1-7 90018

Certificate Information: 3788 S BRONSON AVE 1-7 90018

Application / Permit
24016-10000-13245
Plan Check / Job No.
B24LA07321
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING ATTACHED PARKING GARAGE TO NEW TWO ADUS PER GC & 66323(a)(3) ON AN (E) TWO STORY APARTMENT BUILDING.
Permit Issued
Issued on 7/2/2025
Issuing Office
Metro
Current Status
Issued on 7/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Zoning Architect 5/2/2024 ELAHE MERRIKHI
Assigned to Plan Check Engineer 5/2/2024 TSE MING HUANG
Corrections Issued 5/14/2024 TSE MING HUANG
Quality Review Completed 5/17/2024 KEN GILL
Building Plans Picked Up 5/24/2024 APPLICANT
Applicant returned to address corrections 7/2/2025 SERGIO GUTIERREZ
Plan Check Approved 7/2/2025 SERGIO GUTIERREZ
Issued 7/2/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 6/14/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/25/2024 JESSICA OPINION
Address approval Cleared 4/5/2025 JESSICA OPINION
Green Code Cleared 6/11/2025 MICHAEL MARTINEZ
Zoning Plan Check Cleared 7/2/2025 ELAHE MERRIKHI

Contact Information

Contractor B & C Construction Inc; Lic. No.: 1017702-B 4523 EAST 56TH STREET      MAYWOOD, CA 90270
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2025 Corrections Issued DARRYL ARNOLD
Footing/Foundation/Slab 8/18/2025 Conditional Approval DARRYL ARNOLD
Wood Frame 10/8/2025 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 11/4/2025 No Access for Inspection ALFREDO LOPEZ
Wood Frame 11/4/2025 No Access for Inspection ALFREDO LOPEZ
Pre-Inspection 11/6/2025 Partial Inspection ALFREDO LOPEZ
Insulation 11/10/2025 Approved ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Approved ALFREDO LOPEZ
Drywall Nailing 11/19/2025 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 11/19/2025 Approved ALFREDO LOPEZ
Special/Order Compliance 5/11/2026 Corrections Issued ALFREDO LOPEZ