3865 S DEGNAN BLVD 90008

Certificate Information: 3865 S DEGNAN BLVD 90008

Application / Permit
24016-10000-13234
Plan Check / Job No.
B24LA07315
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. EXISTING GARAGE (348 SF) CONVERSION TO NEW DETACHED ADU (348 SF)
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
CofO Issued on 5/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Plan Check Engineer 4/24/2024 DANIEL SANJUAN
Corrections Issued 4/25/2024 DANIEL SANJUAN
Plan Check Approved 5/14/2024 JOSEPH RAFOLS
Issued 6/28/2024 APPLICANT
CofO in Progress 5/21/2025 LUIS CASTRO
Permit Finaled 5/22/2025 DEROLD HAUFF
CofO Issued 5/22/2025 DEROLD HAUFF
Permit Finaled 5/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 5/9/2024 WALTER RAMIREZ
Address approval Cleared 5/10/2024 AMBER CAMPBELL
Sewer availability Cleared 5/10/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 5/13/2024 LEE GUILBEAUX

Contact Information

Contractor Select Design Construction Inc; Lic. No.: 972421-B       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2024 Partial Approval DAVID FEILER
Deputy Drilled-In Anchors 7/24/2024 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 7/26/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 8/6/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/3/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/5/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 11/22/2024 Corrections Issued BARRY HACHE
Gas Test 11/22/2024 Approved BARRY HACHE
HVAC-Rough 11/22/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 11/22/2024 Approved BARRY HACHE
ELECTRICAL-Rough 12/5/2024 Approved BARRY HACHE
HVAC-Rough 12/5/2024 Approved BARRY HACHE
PLUMBING-Rough 12/5/2024 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 12/5/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 12/11/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Approved BARRY HACHE
Light Gage Steel Frame 12/11/2024 Not Ready for Inspection BARRY HACHE
Reinforced Concrete Frame 12/11/2024 Not Ready for Inspection BARRY HACHE
Reinforced Masonry Frame 12/11/2024 Not Ready for Inspection BARRY HACHE
Structural Steel Frame 12/11/2024 Not Ready for Inspection BARRY HACHE
Insulation 12/19/2024 Approved ALEX COLIN
Drywall Nailing 12/26/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 1/17/2025 Partial Approval ALEX COLIN
Sewer 1/17/2025 Approved ALEX COLIN
Underground Mechanical 1/27/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 2/27/2025 Approved ALEX COLIN
Shower Pan 2/27/2025 Approved ALEX COLIN
ELECTRICAL-Final 5/9/2025 Corrections Issued LUIS CASTRO
Final 5/9/2025 Corrections Issued LUIS CASTRO
HVAC-Final 5/9/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 5/9/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 5/9/2025 Approved LUIS CASTRO
ELECTRICAL-Final 5/14/2025 Approved LUIS CASTRO
Final 5/14/2025 Partial Approval LUIS CASTRO
HVAC-Final 5/14/2025 Approved LUIS CASTRO
PLUMBING-Final 5/14/2025 Approved LUIS CASTRO
Final 5/21/2025 OK to Issue CofO LUIS CASTRO