7712-7714 N BALCOM AVE 91335

Certificate Information: 7712-7714 N BALCOM AVE 91335

Application / Permit
24016-10000-13209
Plan Check / Job No.
B24LA07302
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. EXISTING FAMILY ROOM CONVERSION TO NEW JADU (355SQFT) PER STATE LAW
Permit Issued
Issued on 8/2/2024
Issuing Office
Current Status
CofO Issued on 7/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2024 APPLICANT
Assigned to Plan Check Engineer 4/26/2024 KHUONG TRUONG
Corrections Issued 4/26/2024 KHUONG TRUONG
Plan Check Approved 5/23/2024 JOSEPH RAFOLS
Issued 8/2/2024 APPLICANT
CofO in Progress 6/10/2025 ARUTYUN MADATYAN
Permit Finaled 7/14/2025 JOHN JANSON
CofO Issued 7/14/2025 JOHN JANSON
Permit Finaled 7/14/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2024 TAL SHEMEN
Sewer availability Cleared 5/4/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 5/8/2024 TAL SHEMEN
Public Works-Highway Ded. Cleared 5/14/2024 LEE GUILBEAUX

Contact Information

Contractor Yakov Design & Build; Lic. No.: 1067993-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/7/2024 Approved JEFFREY BULL
Pre-Inspection 11/18/2024 Partial Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/24/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 2/24/2025 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 2/24/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/26/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 3/26/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 3/26/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 3/26/2025 Approved ARUTYUN MADATYAN
Smoke Detectors 3/26/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 5/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 5/27/2025 Approved ARUTYUN MADATYAN
Smoke Detectors 5/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/9/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 6/9/2025 Approved ARUTYUN MADATYAN
Final 6/9/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 6/9/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 6/9/2025 Approved ARUTYUN MADATYAN
Smoke Detectors 6/9/2025 Approved ARUTYUN MADATYAN
Service/Power Release 6/20/2025 Approved ARUTYUN MADATYAN