4639 W 17TH ST 1-10 90019

Certificate Information: 4639 W 17TH ST 1-10 90019

Application / Permit
24016-10000-13205
Plan Check / Job No.
B24LA07293
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERSION OF NON-HABITABLE PARKING & LAUNDRY SPACE TO (2) NEW ADUS PER CA GOVT. CODE 65852.2(e)(1)(C)
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
Issued on 1/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Zoning Architect 4/25/2024 ELAHE MERRIKHI
Assigned to Plan Check Engineer 4/25/2024 SERGIO GUTIERREZ
Corrections Issued 4/29/2024 SERGIO GUTIERREZ
Quality Review Completed 4/29/2024 RODOLFO ARIAS
Applicant returned to address corrections 9/16/2024 SERGIO GUTIERREZ
Plan Check Approved 12/17/2024 SERGIO GUTIERREZ
Issued 1/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/3/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/3/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/3/2024 DAVID LOPEZ
Sewer availability Cleared 6/3/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 6/15/2024 RUEL COLE
DAS Clearance Cleared 7/14/2024 ELIZABETH TOMS
Green Code Cleared 7/17/2024 SERGIO GUTIERREZ
Miscellaneous Cleared 8/21/2024 VARAND SARKISIAN
Tenant Habitability Plan Cleared 12/5/2024 RICARDO BOHORQUEZ
Zoning Plan Check Cleared 12/9/2024 ELAHE MERRIKHI

Contact Information

Architect Driscoll,, Christopher; Lic. No.: NA36073       ,
Contractor All City Builders & Design Inc; Lic. No.: 1075374-B       ,
Contractor Entourage Home Remodeling; Lic. No.: 1075374-B       ,
Engineer Schwartz,, Eric; Lic. No.: C81191 3451 GRIFFITH PARK BLVD      LOS ANGELES, CA 90027
Engineer Schwartz,, Eric; Lic. No.: NA81191       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/22/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Pre-Inspection 3/19/2025 Corrections Issued CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 5/12/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 7/8/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 7/9/2025 Partial Approval CHRISTOPHER BLACKWOOD
Green Building Rough 9/25/2025 Approved MARTIN TAVITIAN
Interior/Exterior Lathing 10/10/2025 Approved MARTIN TAVITIAN
METHANE-Rough 10/10/2025 Approved MARTIN TAVITIAN
Wood Frame 10/10/2025 Approved MARTIN TAVITIAN
Insulation 10/15/2025 Approved CHRISTOPHER BLACKWOOD
Drywall Nailing 10/31/2025 Approved CHRISTOPHER BLACKWOOD
Interior/Exterior Lathing 10/31/2025 Approved CHRISTOPHER BLACKWOOD