1362 W 19TH ST 90732

Certificate Information: 1362 W 19TH ST 90732

Application / Permit
24016-10000-13114
Plan Check / Job No.
B24LA07235
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF SINGLE FAMILY DWELLING OF EXISTING BATHROOM AND KITCHEN - PER ENGINEER.
Permit Issued
Issued on 5/21/2024
Issuing Office
Current Status
Permit Finaled on 2/4/2025

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Plan Check Engineer 4/19/2024 DANIEL ABRAMYAN
Corrections Issued 4/20/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 5/16/2024 GIOVANNY CHAVEZ
Plan Check Approved 5/17/2024 GIOVANNY CHAVEZ
Issued 5/21/2024 APPLICANT
Permit Finaled 2/3/2025 JOSEPH MCGARRY

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/14/2024 MICHAEL TEMPLE

Contact Information

Contractor 5 Blox Inc; Lic. No.: 1036356-B       ,
Contractor 5blox; Lic. No.: 1036356-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/9/2024 Conditional Approval JAMES CHAVEZ
ELECTRICAL-Rough 7/19/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 7/19/2024 Not Ready for Inspection JAMES CHAVEZ
Special/Order Compliance 7/19/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 7/26/2024 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 7/26/2024 Approved JAMES CHAVEZ
Footing/Foundation/Slab 7/26/2024 Approved JAMES CHAVEZ
HVAC-Rough 7/26/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 7/26/2024 Approved JAMES CHAVEZ
HVAC-Rough 8/16/2024 Approved JOSEPH MCGARRY
Insulation 8/16/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/16/2024 Partial Approval JOSEPH MCGARRY
Shower Pan 8/16/2024 Approved JOSEPH MCGARRY
Wood Frame 8/16/2024 Approved JOSEPH MCGARRY
Drywall Nailing 9/3/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/3/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Ready JOSEPH MCGARRY
ELECTRICAL-Final 1/17/2025 Approved EUGENE CASSIDY
Final 1/17/2025 Corrections Issued EUGENE CASSIDY
HVAC-Final 1/17/2025 Approved EUGENE CASSIDY
PLUMBING-Final 1/17/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 1/17/2025 Approved EUGENE CASSIDY
Final 1/28/2025 Corrections Issued ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Ready ANSON MAGLASANG
Final 2/3/2025 Permit Finaled JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved JOSEPH MCGARRY