1461 W 65TH ST 90047

Certificate Information: 1461 W 65TH ST 90047

Application / Permit
24016-10000-12822
Plan Check / Job No.
B24LA07053
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHD GARAGE (2 CAR) TO ADU PER WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 9/26/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 NGHI SU
Corrections Issued 4/23/2024 NGHI SU
Building Plans Picked Up 4/24/2024 APPLICANT
Plan Check Approved 9/26/2024 AUNG SOE
Issued 9/26/2024 APPLICANT
CofO in Progress 1/27/2025 BARRY HACHE
Permit Finaled 2/2/2025 DEROLD HAUFF
CofO Issued 2/2/2025 DEROLD HAUFF
Permit Finaled 2/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/30/2024 JILVER MAZARIEGOS
Sewer availability Cleared 7/30/2024 JILVER MAZARIEGOS
Construction near power lines Cleared 8/26/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/16/2024 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/31/2024 Conditional Approval CRAIG DAVIS
Footing/Foundation/Slab 11/1/2024 Approved CRAIG DAVIS
Pre-Inspection 11/1/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 11/5/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 11/7/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 11/13/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 11/13/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 11/13/2024 Approved CRAIG DAVIS
HVAC-Rough 11/13/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 11/18/2024 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 11/18/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/20/2024 Approved JOSE MACIAS
HVAC-Rough 11/20/2024 Corrections Issued JOSE MACIAS
Special/Order Compliance 11/20/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 11/26/2024 Approved CRAIG DAVIS
HVAC-Rough 11/26/2024 Approved CRAIG DAVIS
Drywall Nailing 12/3/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 12/3/2024 Approved ANTHONY RAMOS
Shower Pan 12/3/2024 Approved ANTHONY RAMOS
Pre-Inspection 12/18/2024 Approved BARRY HACHE
ELECTRICAL-Final 1/15/2025 Corrections Issued BARRY HACHE
HVAC-Final 1/15/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 1/15/2025 Corrections Issued BARRY HACHE
Underground Mechanical 1/15/2025 Approved BARRY HACHE
Final 1/24/2025 OK to Issue CofO BARRY HACHE
Green Building Final 1/24/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Required BARRY HACHE
Smoke Detectors 1/24/2025 Approved BARRY HACHE