1461 W 65TH ST 90047
Certificate Information: 1461 W 65TH ST 90047
- Application / Permit
- 24016-10000-12822
- Plan Check / Job No.
- B24LA07053
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHD GARAGE (2 CAR) TO ADU PER WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | NGHI SU |
| Corrections Issued | 4/23/2024 | NGHI SU |
| Building Plans Picked Up | 4/24/2024 | APPLICANT |
| Plan Check Approved | 9/26/2024 | AUNG SOE |
| Issued | 9/26/2024 | APPLICANT |
| CofO in Progress | 1/27/2025 | BARRY HACHE |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 7/30/2024 | JILVER MAZARIEGOS |
| Construction near power lines | Cleared | 8/26/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/31/2024 | Conditional Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 11/1/2024 | Approved | CRAIG DAVIS |
| Pre-Inspection | 11/1/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 11/5/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 11/7/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/13/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/13/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 11/13/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 11/13/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/18/2024 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/18/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/20/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 11/20/2024 | Corrections Issued | JOSE MACIAS |
| Special/Order Compliance | 11/20/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 11/26/2024 | Approved | CRAIG DAVIS |
| Drywall Nailing | 12/3/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/3/2024 | Approved | ANTHONY RAMOS |
| Shower Pan | 12/3/2024 | Approved | ANTHONY RAMOS |
| Pre-Inspection | 12/18/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 1/15/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 1/15/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 1/15/2025 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 1/15/2025 | Approved | BARRY HACHE |
| Final | 1/24/2025 | OK to Issue CofO | BARRY HACHE |
| Green Building Final | 1/24/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Not Required | BARRY HACHE |
| Smoke Detectors | 1/24/2025 | Approved | BARRY HACHE |