6344 W FOUNTAIN AVE 90028
Certificate Information: 6344 W FOUNTAIN AVE 90028
- Application / Permit
- 24016-10000-12709
- Plan Check / Job No.
- B24LA07003
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Tenant Improvement to (E) Core and Shell space on 3rd and 4th floors
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- Issued on 6/17/2024
Permit Application Status History
| Submitted | 4/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | HERNAN ARREOLA |
| Corrections Issued | 4/22/2024 | HERNAN ARREOLA |
| Quality Review Completed | 4/22/2024 | PETER KIM |
| Applicant returned to address corrections | 5/29/2024 | HERNAN ARREOLA |
| Plan Check Approved | 6/14/2024 | HERNAN ARREOLA |
| Issued | 6/17/2024 | APPLICANT |
| Permit Finaled-Status Void | 4/1/2025 | LUIS CCAMACHO |
| Re-Activate Permit | 6/2/2025 | DAVID BURKHEAD |
Permit Application Clearance Information
| Green Code | Cleared | 5/28/2024 | AARON COSTA |
| DAS Clearance | Cleared | 6/7/2024 | Lawrence Quirante |
Contact Information
| Architect | , ; Lic. No.: C35301 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/28/2024 | Partial Approval | TIMOTHY POWELL |
| Insulation | 8/29/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 8/30/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 9/11/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 9/13/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 9/17/2024 | No Access for Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 9/23/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 10/9/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 10/15/2024 | Partial Approval | LUIS CCAMACHO |
| Pre-Inspection | 12/18/2024 | Partial Inspection | TIMOTHY POWELL |
| Pre-Inspection | 12/24/2024 | Partial Inspection | TIMOTHY POWELL |
| Final | 2/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Final | 2/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 2/1/2025 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 2/1/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 2/5/2025 | Partial Inspection | TIMOTHY POWELL |
| Green Building Final | 2/5/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 2/5/2025 | Approved | TIMOTHY POWELL |
| Final | 3/19/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 3/19/2025 | Approved | LUIS CCAMACHO |
| Drywall Nailing | 8/21/2025 | Partial Approval | LUIS CCAMACHO |
| Final | 9/8/2025 | Partial Inspection | TIMOTHY POWELL |