8 N OAKMONT DR 90049
Certificate Information: 8 N OAKMONT DR 90049
- Application / Permit
- 24016-10000-12608
- Plan Check / Job No.
- B24LA06961
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) 3-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/18/2025
Permit Application Status History
| Submitted | 4/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | CARLOS MONTES |
| Corrections Issued | 5/3/2024 | CARLOS MONTES |
| Quality Review Completed | 5/9/2024 | PRANITA SHAH |
| Plan Check Approved | 6/5/2024 | CARLOS MONTES |
| Issued | 6/6/2024 | APPLICANT |
| Permit Finaled | 8/18/2025 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/14/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Seek Construction Inc; Lic. No.: 1114793-B | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/11/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 8/1/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/7/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/12/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 10/1/2024 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | EVAN COOPER |
| Insulation | 2/25/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/25/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 3/5/2025 | Approved | JESUS RODRIGUEZ |
| Final | 8/7/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 8/7/2025 | Corrections Issued | HERBERT GIRON |
| Final | 8/14/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 8/14/2025 | Approved | KEVIN SARGSYAN |
| Final | 8/18/2025 | Permit Finaled | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | STEPHANIE SWANSON |