8323-8325 S RAMSGATE AVE 90045

Certificate Information: 8323-8325 S RAMSGATE AVE 90045

Application / Permit
24016-10000-12542
Plan Check / Job No.
B24LA06909
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) PER ENGINEERING
Permit Issued
Issued on 2/13/2025
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2024 APPLICANT
Assigned to Plan Check Engineer 4/19/2024 ALFRED RAMIREZ
Corrections Issued 4/19/2024 ALFRED RAMIREZ
Applicant returned to address corrections 6/4/2024 ALFRED RAMIREZ
Plan Check Approved 6/6/2024 ALFRED RAMIREZ
Issued 2/13/2025 APPLICANT
CofO in Progress 4/23/2026 JESUS PINEDA
Permit Finaled 4/23/2026 RICHARD STEINBACH
CofO Issued 4/23/2026 RICHARD STEINBACH
Permit Finaled 4/23/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/2/2024 DARIN LAM
Roof/Waste drainage to street Cleared 5/2/2024 DARIN LAM
Sewer availability Cleared 5/2/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/8/2024 DARIN LAM
Specific Plan Cleared 5/10/2024 GEORGIA SMITH
ZI Cleared 5/10/2024 GEORGIA SMITH
Grading Pre-Inspection Cleared 5/28/2024 VASIL MIHALEV
Hold Cleared 4/29/2025 MARIA VENDIVIL

Contact Information

Contractor Haeun Construction Inc; Lic. No.: 1063420-B       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28531 PALOS VERDES DR EAST      RANCHO PALOS VERDES, CA 90275

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/15/2025 Corrections Issued JESUS PINEDA
Underground Mechanical 6/27/2025 Approved RUBEN RIVAS
PLUMBING-Rough 6/30/2025 Not Ready for Inspection RUBEN RIVAS
Deputy Drilled-In Anchors 7/7/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 8/28/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 11/24/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 11/24/2025 Approved RUBEN RIVAS
Green Building Rough 11/24/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 11/24/2025 Approved RUBEN RIVAS
PLUMBING-Rough 11/24/2025 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 12/8/2025 Approved JESUS PINEDA
Green Building Rough 12/8/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 12/8/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 12/8/2025 Approved JESUS PINEDA
Insulation 1/6/2026 Approved JESUS PINEDA
Drywall Nailing 1/15/2026 Approved JESUS PINEDA
ELECTRICAL-Final 4/1/2026 Approved ANTHONY EGSON
Final 4/1/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Final 4/1/2026 Approved ANTHONY EGSON
HVAC-Final 4/1/2026 Corrections Issued ANTHONY EGSON
PLUMBING-Final 4/1/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved ANTHONY EGSON
Smoke Detectors 4/1/2026 Approved ANTHONY EGSON
Final 4/13/2026 Corrections Issued JESUS PINEDA
HVAC-Final 4/13/2026 Approved JESUS PINEDA
Final 4/23/2026 OK to Issue CofO JESUS PINEDA