7624 S CIMARRON ST 90047
Certificate Information: 7624 S CIMARRON ST 90047
- Application / Permit
- 24016-10000-12489
- Plan Check / Job No.
- B24LA06892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO (N) 360 SF ADU PER GCS 65852.2(e(1)(A). ALL WORK PER ENG.
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Current Status
- Issued on 11/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/19/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/1/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/30/2024 | LUISANGEL VALENZUELA |
| Issued | 11/20/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 4/26/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 8/26/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Mereekh Construction; Lic. No.: 1105804-B | , |
| Contractor | Mereekh Corporation; Lic. No.: 1105804-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/26/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Underground Mechanical | 11/26/2024 | Partial Approval | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 12/13/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 4/24/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 4/24/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Rough | 9/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/27/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 10/27/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/27/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 11/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 11/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/13/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 12/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 12/9/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/24/2026 | Conditional Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/24/2026 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 3/24/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 3/24/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/1/2026 | Approved | MICHAEL LEWIS |
| Insulation | 4/9/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 4/22/2026 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 5/13/2026 | Approved | ALEX COLIN |
| Green Building Rough | 5/13/2026 | Approved | ALEX COLIN |