5163 N HIGHLAND VIEW AVE 90041
Certificate Information: 5163 N HIGHLAND VIEW AVE 90041
- Application / Permit
- 24016-10000-12406
- Plan Check / Job No.
- B24LA06848
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO SINGLE-FAMILY DWELLING WITH DEMO OF WALLS & PORTION OF ATTIC SPACE ON SECOND FLOOR TO HABITABLE SPACE. "COMPLY WITH DEPARTMENT ORDER effective date 03/08/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 5/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 4/19/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/15/2024 | ALEC MOUSAKHANIAN |
| Issued | 5/17/2024 | APPLICANT |
| No Progress | 5/20/2025 | DANIEL DELACRUZ |
| CofO in Progress | 5/20/2025 | DANIEL DELACRUZ |
| Permit Finaled | 5/20/2025 | DANIEL SANCHEZ |
| CofO Issued | 5/20/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/22/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 4/23/2024 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: NA74761 | , |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2024 | Conditional Approval | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 6/5/2024 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 8/14/2024 | Partial Approval | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 8/14/2024 | Approved | DANIEL DELACRUZ |
| Shower Pan | 8/14/2024 | Approved | DANIEL DELACRUZ |
| Underground Mechanical | 8/14/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 8/15/2024 | Approved | DANIEL DELACRUZ |
| Insulation | 8/28/2024 | Partial Approval | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 8/28/2024 | Approved | DANIEL DELACRUZ |
| Drywall Nailing | 9/10/2024 | Approved | DANIEL DELACRUZ |
| Insulation | 9/10/2024 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Pre-Inspection | 9/18/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Approved | DANIEL DELACRUZ |
| Pre-Inspection | 9/25/2024 | Corrections Issued | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 2/24/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Final | 2/24/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Final | 2/24/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| PLUMBING-Final | 2/24/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Not Ready | DANIEL DELACRUZ |
| Smoke Detectors | 2/24/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | DANIEL DELACRUZ |
| Final | 3/3/2025 | Partial Approval | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | DANIEL DELACRUZ |
| Smoke Detectors | 3/3/2025 | Approved | DANIEL DELACRUZ |
| Final | 3/4/2025 | OK to Issue CofO | DANIEL DELACRUZ |