5163 N HIGHLAND VIEW AVE 90041

Certificate Information: 5163 N HIGHLAND VIEW AVE 90041

Application / Permit
24016-10000-12406
Plan Check / Job No.
B24LA06848
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO SINGLE-FAMILY DWELLING WITH DEMO OF WALLS & PORTION OF ATTIC SPACE ON SECOND FLOOR TO HABITABLE SPACE. "COMPLY WITH DEPARTMENT ORDER effective date 03/08/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 5/17/2024
Issuing Office
Current Status
CofO Issued on 5/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 ALEC MOUSAKHANIAN
Corrections Issued 4/19/2024 ALEC MOUSAKHANIAN
Plan Check Approved 5/15/2024 ALEC MOUSAKHANIAN
Issued 5/17/2024 APPLICANT
No Progress 5/20/2025 DANIEL DELACRUZ
CofO in Progress 5/20/2025 DANIEL DELACRUZ
Permit Finaled 5/20/2025 DANIEL SANCHEZ
CofO Issued 5/20/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/22/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 4/22/2024 WALLIE JONG
Sewer availability Cleared 4/22/2024 WALLIE JONG
Grading Pre-Inspection Cleared 4/23/2024 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Kiledjian,, George Zohrab; Lic. No.: NA74761       ,

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/30/2024 Conditional Approval CHARLES BOGHOSKHAN
Footing/Foundation/Slab 6/5/2024 Approved DANIEL DELACRUZ
BUILDING-Rough-Frame 8/14/2024 Partial Approval DANIEL DELACRUZ
ELECTRICAL-Rough 8/14/2024 Approved DANIEL DELACRUZ
Shower Pan 8/14/2024 Approved DANIEL DELACRUZ
Underground Mechanical 8/14/2024 Approved DANIEL DELACRUZ
PLUMBING-Rough 8/15/2024 Approved DANIEL DELACRUZ
Insulation 8/28/2024 Partial Approval DANIEL DELACRUZ
Interior/Exterior Lathing 8/28/2024 Approved DANIEL DELACRUZ
Drywall Nailing 9/10/2024 Approved DANIEL DELACRUZ
Insulation 9/10/2024 Approved DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Not Ready for Inspection DANIEL DELACRUZ
Pre-Inspection 9/18/2024 Not Ready for Inspection DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved DANIEL DELACRUZ
Pre-Inspection 9/25/2024 Corrections Issued DANIEL DELACRUZ
BUILDING-Rough-Frame 2/24/2025 Not Ready for Inspection DANIEL DELACRUZ
ELECTRICAL-Final 2/24/2025 Not Ready for Inspection DANIEL DELACRUZ
Final 2/24/2025 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Final 2/24/2025 Not Ready for Inspection DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Not Ready DANIEL DELACRUZ
Smoke Detectors 2/24/2025 Not Ready for Inspection DANIEL DELACRUZ
BUILDING-Rough-Frame 3/3/2025 Approved DANIEL DELACRUZ
Final 3/3/2025 Partial Approval DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 3/3/2025 SGSOV Approved DANIEL DELACRUZ
Smoke Detectors 3/3/2025 Approved DANIEL DELACRUZ
Final 3/4/2025 OK to Issue CofO DANIEL DELACRUZ