5601 W HOLLYWOOD BLVD 90028
Certificate Information: 5601 W HOLLYWOOD BLVD 90028
- Application / Permit
- 24016-10000-12341
- Plan Check / Job No.
- B24LA06812
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment Hotel
- Work Description
- ePLAN. **PROJECT HOMEKEY** PROVIDE ACCESSIBLE ENTRANCE. VOLUNTARY ACCESSIBLE UPGRADES TO TWO UNITS. ONE COMMUNICATION AND MOBILITY UNIT PROVIDED. TENANT IMPROVEMENT TO (E) APARTMENT HOTEL
- Permit Issued
- Issued on 11/18/2024
- Issuing Office
- Current Status
- Permit Finaled on 12/22/2025
Permit Application Status History
| Submitted | 4/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | KEVIN MORALES |
| Corrections Issued | 5/2/2024 | KEVIN MORALES |
| Quality Review Completed | 5/2/2024 | EUGENE BARBEAU |
| Plan Check Approved | 6/27/2024 | KEVIN MORALES |
| Issued | 11/18/2024 | APPLICANT |
| Permit Finaled | 12/22/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Public Housing | Cleared | 5/8/2024 | DANIEL COLLINS |
| City Hist. Cultural Monument | Cleared | 6/17/2024 | RAFAEL FONTES |
| DAS Clearance | Cleared | 6/17/2024 | Eugene Barbeau |
| Historic monument | Cleared | 6/17/2024 | RAFAEL FONTES |
| Density Bonus | Cleared | 6/21/2024 | MARITES CUNANAN |
Contact Information
| Architect | Kadribegovic,, Nerin; Lic. No.: NA32104 | , |
| Contractor | Chait & Company; Lic. No.: 704592-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2025 | Approved | TIMOTHY POWELL |
| Masonry Wall/Backfill | 4/10/2025 | Partial Approval | MARTIN TAVITIAN |
| Deputy Drilled-In Anchors | 5/12/2025 | Conditional Approval | RAFAEL CORTES |
| Deputy Steel/Welding | 5/12/2025 | Conditional Approval | RAFAEL CORTES |
| Structural Steel Frame | 5/27/2025 | No Access for Inspection | RAFAEL CORTES |
| Wood Frame | 5/27/2025 | No Access for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 5/29/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 5/29/2025 | Corrections Issued | RAFAEL CORTES |
| Wood Frame | 6/5/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 6/11/2025 | Corrections Issued | RAFAEL CORTES |
| Wood Frame | 6/13/2025 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 7/15/2025 | Partial Approval | LUIS CCAMACHO |
| Wood Frame | 7/16/2025 | Partial Inspection | LUIS CCAMACHO |
| Wood Frame | 7/17/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Concrete Frame | 7/21/2025 | Partial Approval | LUIS CCAMACHO |
| Insulation | 7/29/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 8/8/2025 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 8/12/2025 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 8/13/2025 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 9/24/2025 | Partial Inspection | ALFREDO LOPEZ |
| Structural Steel Frame | 9/26/2025 | Partial Approval | LUIS CCAMACHO |
| Final | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 10/20/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 11/25/2025 | Corrections Issued | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 11/25/2025 | Approved | RAFAEL ESPINOZA |
| Final | 12/9/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Final | 12/22/2025 | Permit Finaled | RAFAEL ESPINOZA |