5800 N MONTEREY ROAD 90042
Certificate Information: 5800 N MONTEREY ROAD 90042
- Application / Permit
- 24016-10000-12198
- Plan Check / Job No.
- B24LA06746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- (eplan) Change of Use from (E) Retail to Restaurant and Tenant Improvement including alteration to existing wood framed facade and structural support for mechanical units on roof . <Not sprinklered>
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2024 | APPLICANT |
| Assigned to Zoning Architect | 4/18/2024 | ERIC ROMERO |
| Assigned to Plan Check Engineer | 4/18/2024 | YOUNG KIM |
| Corrections Issued | 4/24/2024 | YOUNG KIM |
| Quality Review Completed | 5/8/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/16/2024 | YOUNG KIM |
| Applicant returned to address corrections | 7/23/2024 | YOUNG KIM |
| Applicant returned to address corrections | 7/25/2024 | YOUNG KIM |
| Applicant returned to address corrections | 8/20/2024 | YOUNG KIM |
| Applicant returned to address corrections | 8/27/2024 | YOUNG KIM |
| Plan Check Approved | 9/13/2024 | YOUNG KIM |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 10/16/2025 | RONALD JIMENEZ |
| Permit Finaled | 10/16/2025 | ERNESTO CORRAL |
| CofO Issued | 10/16/2025 | ERNESTO CORRAL |
| Permit Finaled | 10/16/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/20/2024 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 7/25/2024 | YOUNG KIM |
| Green Code | Cleared | 7/28/2024 | George Alvarez |
| DAS Clearance | Cleared | 8/1/2024 | George Alvarez |
| Food establishment approval | Cleared | 8/20/2024 | LACDHS APPROVED |
| Sewer availability | Cleared | 8/27/2024 | WALLIE JONG |
| Food Service Establishment | Cleared | 8/28/2024 | PAWAN VERMA |
| ZA Case | Cleared | 9/5/2024 | GRACIELA ACOSTA |
| Comm Cor/Mini-Mall | Cleared | 9/6/2024 | DAVID URITA |
| Comm Cor/Mini-Mall | Cleared | 9/6/2024 | DAVID URITA |
| Comm Cor/Mini-Mall | Cleared | 9/6/2024 | DAVID URITA |
| Zoning Plan Check | Cleared | 9/9/2024 | George Alvarez |
Contact Information
| Architect | Wick, Architecture & Design; Lic. No.: NA29199 | 2101 PARK DRIVE LOS ANGELES, CA 90026 |
| Contractor | J B C I; Lic. No.: 979172-B | , |
| Engineer | Valancius,, Joseph; Lic. No.: S3609 | 60620 E ARROYO VISTA DR ORACLE, AZ 85623 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 1/28/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 1/28/2025 | Partial Approval | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 1/30/2025 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 2/3/2025 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 2/5/2025 | Partial Approval | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 3/3/2025 | Approved | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 3/3/2025 | Approved | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 5/27/2025 | Partial Approval | JEROME BLACKWOOD |
| Final | 9/30/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 9/30/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 9/30/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 9/30/2025 | Approved | JEROME BLACKWOOD |
| Wood Frame | 9/30/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 10/6/2025 | OK to Issue CofO | RONALD JIMENEZ |
| Green Building Final | 10/6/2025 | Approved | RONALD JIMENEZ |
| Green Building Rough | 10/6/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 10/6/2025 | Approved | RONALD JIMENEZ |